Last Update: 09/22/2026 at 11:34 PM EST

Texas Screens Data Center Power Requests

Coverage from Houston Public Media, Keentel Engineering, and others

Texas Screens Data Center Power Requests topic image

ERCOT and the Texas Public Utility Commission are replacing largely individual reviews of large data center power requests with a batch process beginning with Batch Zero.

The rules are intended to distinguish projects with land, financing, equipment, and other evidence of readiness from speculative requests while allocating limited transmission capacity; later projects may face multi-year waits. ERCOT is also advancing requirements for data centers and other large loads to remain online during brief grid disruptions, although implementation details and project prioritization remain unsettled.

Looking Back
20 Day Timeline
May 30Jun 3Jun 7Jun 9Jun 13Jun 17
All Articles9 articles
Important2 articles · CI Score 60 and above
Houston Public Media
ERCOT approved Batch Zero, a batch-study process for Texas data-center large-load interconnection, and plans a June 18 Public Utility Commission of Texas vote.
6/2/2026 • Power Procurement & Grid • General
Keentel Engineering / Sandip R. Patel
ERCOT testimony in April 2026 described BYOG, CLR, and WLPUN and Batch Zero updates to manage Texas data center Large Load interconnection.
5/30/2026 • Power Procurement & Grid • General
Interesting6 articles · CI Score 45–59
Politico
ERCOT advanced batched interconnection review and data-center ride-through requirements in Texas for Public Utility Commission action.
6/3/2026 • Power Procurement & Grid • General
Houston Public Media
ERCOT will vote on a new batched process for evaluating Texas data-center interconnection requests on Tuesday after hundreds of gigawatts of proposals entered the queue.
6/1/2026 • Policy & Utility Planning • General
Houston Public Media / Natalie Weber
ERCOT will vote Tuesday on Batch Zero, a batch review process to filter data center interconnection requests amid Texas load growth and transmission planning constraints.
6/1/2026 • Policy & Utility Planning • General
E&E News by POLITICO / Shelby Webb
Texas regulators approved Batch Zero interconnection rules for data centers under ERCOT on the first group of projects, lowering nonrefundable fees.
6/18/2026 • Policy & Utility Planning • General
E&E News by POLITICO / Shelby Webb
ERCOT board approved Batch Zero and ride-through rules for data centers in Texas, with PUC review scheduled and large-load requests totaling about 450 GW.
6/3/2026 • Policy & Utility Planning • General
Texas Standard / Natalie Weber
ERCOT will vote Tuesday on a batch-based interconnection evaluation process for Texas data centers to screen speculative projects amid rapid load growth.
6/2/2026 • Policy & Utility Planning • General
Additional1 article · CI Score below 45
KERA News
ERCOT will vote Tuesday on a batch-based interconnection process for Texas data centers, starting with Batch Zero, to screen speculative projects and improve grid reliability.
6/2/2026 • Policy & Utility Planning • General