Last Update: 09/22/2026 at 11:34 PM EST
Texas Shifts Data Center Grid Costs
Coverage from KBTX, Houston Public Media, and others

Texas Gov.
Greg Abbott has directed state regulators to develop measures requiring data centers to cover the electricity infrastructure costs associated with their grid connections. The effort also targets tax incentives, water use, noise, and community impacts as data center proposals grow across the state. Regulators must report on available actions by July 17, while ERCOT and local governments face pressure to manage connection demand and limited local authority.
Looking Back
9 Day Timeline
Jun 3
Jun 4
Jun 6
Jun 7
Jun 8
Jun 10
Jun 11
All Articles4 articles
Additional
6/10/2026 • Power Procurement & Grid • General
6/10/2026 • Policy & Utility Planning • General
6/11/2026 • Policy & Utility Planning • General
6/3/2026 • Policy & Utility Planning • General