Data Center Approval Risks Depend on Where and When
A Minneapolis council committee has advanced a conditional route for downtown data centers, while a Salisbury conversion remains on hold and a Missoula developer is challenging local zoning rules. Each faces a different path to approval.
A separate post-election assessment suggests longer-dated projects may be more exposed to regulatory delays than capacity already under construction. That is a forecast of risk, not evidence of a nationwide construction slowdown.
Minneapolis is considering a limited reopening. The committee-backed proposal would allow data centers within mixed-use properties in two downtown districts, cap server space at 150,000 square feet, and require setbacks and disclosures about resource use and noise. GovTech reports that the full council is scheduled to vote November 12, before the moratorium expires November 21.
TrendForce sees increased delay risk after the midterms, particularly for capacity planned for 2028 and later; it says much of the 2027 pipeline is already under construction. Its state classifications are analytical judgments, and the available assessment does not establish project-level exposure. Texas governor-elect Gina Hinojosa’s stated intention to delay permits pending resident protections is not yet an enacted restriction.
In Missoula, CubCloud AI is challenging the city’s zoning ordinance under Montana’s Right to Compute Act. KECI reports that the founder has put plans for a two- or three-megawatt facility on hold. The city intends to defend its rules; there is no ruling or litigation timetable in the available reporting.
In Salisbury, review of a proposed conversion of the former Cadista pharmaceutical plant remains paused during a one-year moratorium. Owner Vishal Patel says he invested in plans after receiving a city letter; officials say the project was never approved, and records show no approval. The letter’s meaning remains unresolved.
Key Points
- Recent briefings documented substantial opposition in public comments. Minneapolis now offers a concrete pending council decision, but its overwhelmingly opposed comments do not establish how the full council will vote.
- A proposed ordinance, an active review hold and a court challenge all create approval risk, but they do not imply the same timetable or outcome. The distinction matters when assessing individual projects.
Implications
For delivery forecasts, construction-stage capacity should be distinguished from unbuilt plans: TrendForce’s assessment places greater potential exposure in the latter, though it does not quantify affected projects.
Salisbury illustrates how spending on plans before formal approval can be exposed to a review hold, even where an owner has received a city letter.
Watchpoints
Watch
The Minneapolis council’s November 12 vote and the treatment of the moratorium expiring November 21.
Watch
Missoula court filings, any interim relief and the interpretation of the Right to Compute Act.
Watch
Binding state measures following the elections, including whether they affect projects already under construction, and any project-level changes to 2028-and-later schedules.
Watch
Disclosure of Salisbury’s city letter and the conditions for resuming review.
Fallout
Local approval remains a project-specific constraint, while post-election policy risk is emerging as a longer-horizon forecasting question.
Minneapolis downtown siting
The city is weighing conditional development rather than an unrestricted reopening.
Fresh developments
A council committee recommended the ordinance on November 9. It would limit server space, require setbacks and call for resource-use and noise-control disclosures.
Why we noticed
The proposal offers a defined route for limited downtown development, but neither the ordinance nor a specific project has been approved.
Watch for:
- The November 12 full council vote and what happens before the moratorium expires November 21.
Post-election project risk
Potential policy changes could affect unbuilt capacity differently from projects already under construction.
Fresh developments
TrendForce assesses higher delay risk in Texas, Georgia and Ohio, rates Wisconsin high risk and Oregon severe, and identifies projects planned for 2028 and later as most exposed.
Why we noticed
The assessment is useful for testing delivery assumptions, but its classifications are judgments and the available reporting lacks project-level exposure data and methodology.
Watch for:
- Enacted orders or legislation and their treatment of active construction.
- Revised delivery schedules for specific 2028-and-later projects and the scope of any Oregon permit-pause order.
Missoula zoning challenge
A local siting dispute is testing the relationship between municipal rules and Montana’s Right to Compute Act.
Fresh developments
CubCloud AI is seeking revised zoning rules, while its founder says a proposed two- or three-megawatt facility is on hold. The city plans to defend the ordinance.
Why we noticed
The case could clarify local authority, but its legal merits and wider applicability remain unsettled.
Watch for:
- Court filings, interim relief and any ruling on the ordinance.
Salisbury conversion hold
A moratorium continues to block review of a proposed former-plant conversion.
Fresh developments
Current reporting clarifies a dispute over a city letter: the owner says he invested in plans after receiving it, while officials say the project was never approved.
Why we noticed
The review hold is a concrete project impediment; the letter’s contents and legal significance have not been established.
Watch for:
- The letter’s disclosure and any conditions or timetable for restarting review.
Final Thought
The clearest evidence of delay remains project-specific. The broader post-election risk to future capacity is an assessment to test, not yet a measured construction slowdown.