Spanish data-center campus projects range from proposals and early permitting to approved infrastructure and preparation for construction.
Examples include Nostrum Evergreen in Badajoz, Digital Valley Asturias in Salas, and Ferrovial Digital Infrastructure’s phased campus near Madrid. Their plans vary in scale and location, while commonly raising questions about site selection, project phasing, and the power infrastructure needed to support high-capacity computing. Some developments also connect campus plans with renewable generation, as in the Ignis–Acciona project in Segovia.
Looking Back
60 Day Timeline
Jul 14
Jul 24
Aug 3
Aug 13
Aug 21
Aug 31
Sep 10
All Articles6 articles
Important
Data Riocaya received preliminary authorization in Extremadura, Spain, for substations and underground transmission lines supporting the planned Nostrum Evergreen data center.
9/11/2026 • Power Procurement & Grid • General
Interesting
Ignis and Acciona formalized a joint venture developing a renewable-powered data center project and adjacent solar plant in Segovia, Spain.
8/22/2026 • Power Procurement & Grid • General
Additional
Vapat is proposing a 160MW data center campus through DC Mudarra in Torrelobaton, Spain, with construction contingent on environmental approval.
8/21/2026 • Infrastructure & Site Development • General
Ferrovial Digital Infrastructure begins earthworks for the MAD01 60MW phase of a phased data center campus in Alcobendas, Madrid, under a Special Interest designation.
7/14/2026 • Infrastructure & Site Development • General
The Principality of Asturias announced Digital Valley Asturias, a 1.226 billion euro data center campus planned for Salas, Spain, with construction scheduled for 2027-2030.
8/5/2026 • Infrastructure & Site Development • General
Valfortec started administrative permitting for a roughly 60MW data center campus in Elche, Spain, with about EUR 300 million investment pending approvals.