OpenAI's Georgia Campus Faces Scrutiny
Coverage from Georgia Recorder, The Atlanta Journal-Constitution, and others

OpenAI plans Project Camellia, a roughly $20 billion data center campus in Effingham County near Savannah, with Georgia Power set to supply up to 3.
2 gigawatts in phases from 2028 to 2032. The Georgia Public Service Commission approved the power contract, which includes up to 1 gigawatt of flexible demand response; OpenAI says it will cover the project's infrastructure costs and use closed-loop cooling. Residents and policymakers continue to seek clarity on electricity costs, water, noise, community commitments, and remaining reviews, as Georgia debates how to regulate new data centers.
If you read one thing
This broad overview introduces the campus and its major power, water, tax, and infrastructure implications.
Best explainer
It explains how the approved power contract allocates infrastructure and cancellation risks while allowing demand response.
The counter-case
It presents the statewide-moratorium position and connects local opposition to the broader policy dispute.
Latest development
This recent story-driver update shows how the debate has entered Georgia’s gubernatorial race, including competing approaches to oversight.
Utility approval secured, build-readiness unresolved
Project Camellia has cleared Georgia Power's contract stage, but it remains pre-construction. County site-plan, water and sewer arrangements, environmental disclosures, and additional state reviews remain outstanding.
Exceptional grid demand with formal cost protections
The approved Georgia Power commitment represents roughly 3.1–3.2 gigawatts, an unusually large prospective load. OpenAI is assigned infrastructure and termination obligations and may reduce demand during peaks, but stranded-cost exposure and contract transparency remain contested.
Local consent dispute is gaining institutional force
Residents continue to oppose the project over limited advance notice, noise and safety risks, infrastructure impacts, and the need for enforceable commitments. Scrutiny has expanded from county meetings into PSC hearings and broader demands for disclosure and safeguards.
Water and wastewater capacity remain constraints
OpenAI presents closed-loop cooling as a way to limit ongoing water demand, but wastewater treatment, aquifer access, distribution capacity, and environmental disclosure remain unsettled. These issues continue to shape county review and resident opposition.
Tax incentives and community benefits define the local bargain
Supporters emphasize projected tax revenue, jobs, education, workforce programs, and OpenAI's proposed $80 million community package. The value proposition remains contested because the project also receives a 50% property-tax abatement for 15 years, keeping foregone revenue and benefit enforceability central to the debate.
15 years
duration of property tax abatement
“Brant Herndon, CEO of the Effingham County Industrial Development Authority, previously told Savannah Morning News that the IDA board approved an incentives package including a 50% property tax abatement for 15 years. In exchange, OpenAI would be locked into the county’s 2026 millage rate for the duration of the agreement.”
1,000 megawatts MW
maximum electricity that could be diverted to other customers
“OpenAI has also agreed to allow Georgia Power to reduce electricity delivered to the facility during periods of high system demand. As much as 1,000 megawatts could be diverted to other customers. The article describes the agreement as the first of its kind in the nation.”
15 days
deadline for Georgia Power to notify the PSC after early termination
“If a large-load customer terminates early, Georgia Power must notify the PSC within 15 days and cannot shift cost deficiencies to residential or small-business customers.”
3.2 gigawatts
power supply for the Effingham County data center
“On Aug. 26, the Georgia Public Service Commission approved a contract allowing Georgia Power to supply 3.2 gigawatts of power to the Effingham County data center, an amount described as equivalent to the electricity use of about 2 million homes.”
four and a half hours
meeting duration
“More than 100 residents attended a Saturday meeting at the Effingham County Board of Commissioners chambers to hear a presentation and raise questions about the recently announced proposal. The meeting lasted four and a half hours, including three hours of public comment, during which residents overwhelmingly opposed the project.”
Contested Issue
Should Project Camellia and other Georgia data-center projects proceed under local decision-making and negotiated protections, or should new construction pause pending broader review and statewide standards?
The corpus presents incompatible policy approaches: one favors local project decisions with stricter requirements and utility protections, while the other calls for a statewide pause until community, environmental, and cost concerns are assessed and standards are developed.
Local decisions with safeguards
Allow projects to advance through local decision-making while applying guardrails, transparency requirements, and protections for electricity customers.
Pause pending statewide review
Pause new data-center construction until broader review addresses community impacts, environmental safeguards, transparency, and potential effects on utility bills, then establish statewide standards.
Georgia’s data-center rules become a gubernatorial campaign divide
About 20 data-center regulatory bills stalled in Georgia’s 2026 legislative session, and the governor’s race now features opposing approaches: Keisha Lance Bottoms proposes a temporary statewide construction pause to develop standards, while Rick Jackson favors local approval authority with stricter requirements and greater cost transparency.
Previously
OpenAI is proposing a roughly $20 billion data center campus, Project Camellia, at the Savannah Gateway Industrial Hub near Rincon, Georgia. The project could receive up to 3.2 gigawatts from Georgia Power between 2028 and 2032, while OpenAI says it will fund required power infrastructure, use closed-loop cooling and provide community investments. Its scale has prompted scrutiny over electricity costs, water, noise, tax abatements, transparency and the remaining county and state reviews.
The main new detail is OpenAI’s planned $80 million community fund. The current account also highlights disagreement over whether data center development should be paused or governed through local decisions and stronger requirements.
The Georgia Public Service Commission has now approved the power contract, moving Project Camellia beyond proposed utility review while county and other state reviews remain. The story is increasingly framed around balancing projected economic benefits against unresolved oversight and community concerns.