NorthPoint Development has discussed a possible data center at the 45-acre former FMC site near Graphics Drive in Modesto, California, but no formal application has been filed.

Large data centers are not allowed under the city's current code, so any proposal would require zoning changes, CEQA review, public hearings, and approval by the Planning Commission and City Council. Residents and some local officials are pressing for a moratorium or ban, citing potential effects on electricity demand, utility rates, water use, noise, emissions, and site-related environmental concerns.

Looking Back
17 Day Timeline
Aug 3Aug 6Aug 9Aug 13Aug 16Aug 19
History
08/24/2026

The story has shifted from tentative local concern to organized opposition, including calls for a moratorium or permanent ban. County officials have also entered the discussion by reviewing potential impacts, although no formal county policy or project application exists.

All Articles9 articles
Additional9 articles · CI Score below 45
The Modesto Bee / Ken Carlson
8/6/2026 • Permitting & Regulation • General
KCRA / Karson Wells
8/9/2026 • Community & Local Opposition • General
Modesto Bee / Ken Carlson
8/3/2026 • Infrastructure & Site Development • General
Data Center Dynamics / Jemima Davey
8/19/2026 • Community & Local Opposition • General
CBS News Sacramento
8/13/2026 • Community & Local Opposition • General
City of Modesto
8/12/2026 • Permitting & Regulation • General
Modesto Bee
8/12/2026 • Community & Local Opposition • General
Modesto Bee / Ken Carlson
8/11/2026 • Permitting & Regulation • General
Modesto Bee / Ken Carlson
8/14/2026 • Permitting & Regulation • General