Cities Pause Data Center ApprovalsCities Pause Data Center ApprovalsCoverage from Spectrum News Kentucky, JD Supra, and others
00/00/0000
DailyWeekly
Louisville is using a six-month moratorium and proposed zoning rules to pause new data center approvals while officials consider limits on facility size, location, noise, cooling, setbacks, and infrastructure costs.
Similar pauses in North Carolina and proposals elsewhere show communities seeking more control over electricity demand, water use, utility rates, environmental impacts, and public participation before approving large facilities. The regulatory direction remains unsettled, with existing projects often grandfathered or exempted and permanent rules still moving through local and state processes.
It adds broader evidence on how power and water constraints shape permitting while major data center projects continue moving forward.
Las Vegas Review-Journal
Key Issues
01
Moratoria are hardening into siting rules
Louisville, Raleigh, Cary, Charlotte, and other jurisdictions are using temporary pauses to develop tighter controls on facility size, location, setbacks, noise, hearings, and environmental review. Louisville’s advancing code amendments and the spread of additional pauses indicate that moratoria are increasingly serving as bridges to permanent local standards.
Strengthening
Drawn from 4 articles
02
Resource impacts are becoming approval conditions
Electricity demand, water use, cooling systems, utility costs, and infrastructure capacity are increasingly being addressed through developer-funded upgrades, resource-impact reviews, cooling restrictions, and proposed state standards. These concerns are shaping both local moratoria and the substantive rules being drafted for eventual approvals.
Stable
Drawn from 5 articles
03
Local control is fragmented and legally contested
The effect of new restrictions depends on state authority, procedural rules, and project status. Lawsuits over moratoria, differing municipal approaches, and explicit exemptions or grandfathering for approved or advancing facilities continue to limit uniform application of local controls.
Strengthening
Drawn from 5 articles
04
Large projects continue under regulatory friction
Moratoria are slowing or conditioning future approvals rather than eliminating the development pipeline. Exempt or grandfathered Louisville projects, Cleveland’s proposed 150-MW facility, and major Nevada power requests show that substantial investment remains active alongside tighter review.
Stable
Drawn from 5 articles
Key Numbers
5-3
Planning Commission vote
recommendation of Land Development Code amendments
“Louisville Metro is moving closer to new data center regulations after the Louisville Metro Planning Commission voted 5-3 to recommend amendments to the Land Development Code.”
Spectrum News Kentucky
six-month
application moratorium duration
data center applications
“A six-month moratorium on data center applications took effect in August, but it could end early if Metro Council approves regulations sooner.”
Spectrum News Kentucky
100 or 200 feet
required setback from residential areas
depending on facility size
“Depending on their size, data centers would have to be located 100 or 200 feet from nearby residential areas.”
Spectrum News Kentucky
500,000 square feet
maximum data center size
under the draft amendments
“Under the draft amendments, data centers would be capped at 500,000 square feet and allowed only in the M-1 industrial zoning district. Facilities larger than 50,000 square feet would require a conditional use permit.”
Spectrum News Kentucky
50,000 square feet
threshold for conditional use permit
facilities larger than this threshold
“Under the draft amendments, data centers would be capped at 500,000 square feet and allowed only in the M-1 industrial zoning district. Facilities larger than 50,000 square feet would require a conditional use permit.”
Spectrum News Kentucky
Contested Issue
1 open dispute
Should local governments temporarily pause new data center approvals, or allow projects to proceed under clear standards without a moratorium?
The corpus presents incompatible regulatory approaches. Multiple jurisdictions are using or considering temporary moratoria to study data centers' infrastructure, resource, environmental, and neighborhood effects before approving additional projects. Other evidence favors clear, case-by-case standards and zoning controls instead of broad pauses, allowing investment to proceed while impacts are addressed.
Temporary approval pauses
3 articles · across 3 publications
Local governments should suspend or restrict new approvals while they develop comprehensive siting, resource-use, infrastructure, and environmental standards.
Standards without moratoria
3 articles · across 3 publications
Local governments should use clear, case-by-case standards and zoning controls rather than broadly suspending approvals, allowing data center investment to proceed while impacts are assessed and mitigated.
Looking Back
133 Day Timeline
Articles published over time. Hover any bar for the period and its article count.
May 7
May 28
Jun 21
Jul 12
Aug 2
Aug 26
Sep 16
The Story So Far
No material change
Raleigh’s consideration of a six-month moratorium reinforces the existing pattern of North Carolina communities pausing or constraining data center approvals, but does not materially change the topic’s established regulatory direction.
Previously
Louisville is using a six-month moratorium and proposed zoning rules to pause new data center approvals while officials consider limits on facility size, location, noise, cooling, setbacks, and infrastructure costs. Similar pauses in North Carolina and proposals elsewhere show communities seeking more control over electricity demand, water use, utility rates, environmental impacts, and public participation before approving large facilities. The regulatory direction remains unsettled, with existing projects often grandfathered or exempted and permanent rules still moving through local and state processes.
History
09/09/2026
The story broadens from Louisville’s moratorium to a wider, unsettled regulatory movement, with more North Carolina jurisdictions and Seattle entering the picture. It also sharpens the dispute over grandfathering existing projects and adds ownership disclosure to Louisville’s proposed rules.
09/08/2026
Louisville’s response has advanced from a moratorium and proposed framework to a formal planning process, with the Planning Commission recommending more detailed zoning and operating requirements.
Louisville Metro's Planning Commission recommended data center zoning amendments in Louisville, Kentucky, imposing size, setback, permitting, environmental, generator, and cooling requirements before Metro Council review.
Multiple U.S. states and localities proposed or advanced data center moratoria and zoning changes in 2025-2026, increasing permitting delays and litigation risk.
Louisville Mayor Craig Greenberg signed a six-month data center moratorium Friday in Louisville, Kentucky, after Metro Council approved new siting restrictions.
Louisville Metro Council approved a six-month moratorium on new data center proposals in Louisville, Kentucky, while officials develop zoning and siting regulations.
Louisville Metro Council approved a 180-day moratorium on new data center proposals in Louisville, Kentucky, while permanent siting regulations undergo review.
Dermody Properties filed a Louisville application to convert a vacant Rubbertown warehouse into a data center while city officials consider a moratorium on new facilities.
Louisville Mayor Craig Greenberg directed officials on Aug. 12 to pause Dermody Properties' proposed Kramers Lane data center while Metro Council considers a 180-day moratorium.
The Frey administration proposed Minneapolis data center zoning rules for downtown and commercial corridors, with a public hearing scheduled October 13 and a City Council vote planned for November.
Ben Murray and Manchester, Ohio residents used township hearings and a PJM site request to challenge a proposed data center, resulting in a one-year pause and moratoriums in 2026.
5/28/2026 • Community & Local Opposition • General
Cary Town Council approved an immediate 18-month moratorium on data center approvals in Cary, North Carolina, through February 2028, while officials study regulation and infrastructure capacity.
Mercer County Fiscal Court approved a one-year data center construction moratorium in Kentucky after residents opposed Panattoni Data Centers' proposed 1,300-megawatt hyperscale facility.
Cleveland City Council voted in 2020s to pause standalone data center development for three months, directing staff to draft zoning rules for Cleveland-area sites.
Eagan Capital sued Eagan, Minnesota on June 15 to block enforcement of a one-year data center moratorium adopted in February amid interim permit denials and noise complaints.
Henderson, Nevada considered a 180-day moratorium on data center permit approvals as NV Energy weighs major grid load requests and environmental groups push tighter local rules.
Madison officials planned draft hyperscale data center zoning rules for fall after a January moratorium, while Dane County approved a moratorium extending to December 2027.
First & Utah Properties submitted June 12 filings to convert 45,600 square feet at 2401 Utah Ave. S. into a small-scale Seattle data center under a new large data center moratorium.
Louisville Metro Office of Planning opened a 30-day public comment period for draft data center regulations on Tuesday, proposing a hyperscale ban and tighter siting limits.
Charlotte City Council approved a five-month data center moratorium on Monday, after resident concerns about clean air and clean water and state-law limits on pending approvals.
Dane County Board Chair Patrick Miles advances a permitting-focused moratorium on hyperscale data center proposals after legal review of Manitowoc County's approach, pending a June 4 vote.
Eagan, Minnesota, and other U.S. jurisdictions use temporary data center moratoria as legal authority, preemption, and Takings risks are evaluated locally.
Cleveland officials seek a three-month to one-year moratorium on data-center zoning permits during zoning-code updates, affecting H5 and Lakeland projects.
Lakeland Equity Group filed plans on May 5 for a 150 MW hyperscale data center in Cleveland's Slavic Village as City Council debates a moratorium timing decision.
Cary Town Council approved an 18-month moratorium on new large-scale data centers in Cary, North Carolina, to study infrastructure, water, land-use, and environmental requirements.
Louisville Metro Council approved a six-month moratorium on new data center applications Thursday in Louisville, Kentucky, after public opposition and concerns about land-use impacts.
Louisville Metro Council approved a six-month data center moratorium Thursday in Louisville, Kentucky, to study zoning, infrastructure, utility, water, tax, and neighborhood impacts.
Louisville Mayor Craig Greenberg plans to pause a newly submitted southwest Louisville data center application while Metro Council considers a six-month moratorium and new local rules.
Louisville Metro Government released a June 9, 2026 draft data center land development code amendment for comment, and Kentucky Resources Council submitted revisions on notice and lifecycle standards.
Michael J. Morell said Cleveland should reject a three-month data center permit moratorium and continue permitting with clear standards, citing U.S. AI investment competitiveness.
Kentucky Resources Council submitted an impact-based model ordinance to Louisville and Lexington during public comment on proposed hyperscale data center zoning changes.
Minneapolis officials paused new data center development for five months in Minneapolis while reviewing proposed zoning, resource-use, safety, and neighborhood regulations.
Louisville's Planning Commission advanced stricter data center regulations Thursday in Louisville, including rezoning requirements and a proposed hyperscale ban, for final consideration by Metro Council.
A North Carolina town launched a data center information portal during a 12-month pause to study infrastructure, environmental, and community impacts before revising local zoning rules.
Louisville Mayor Craig Greenberg urged the city council on Tuesday to pause data center construction while Louisville, Kentucky, considers new siting regulations.
Burgin, Kentucky advanced a data center annexation ordinance on July 9, while Harrodsburg and Mercer County officials questioned notice rules, services, and water supply capacity.
Jackson City Council considered a six-month data center development moratorium on July 14, after a draft ordinance and a northwest Jackson rezoning application remained pending.
Lakeland Equity Group filed a Cleveland permit for a 150 MW Slavic Village hyperscale data center as Mayor Justin Bibb and City Council weigh a moratorium.
Morgan McGarvey urged LG&E and KU to prevent ratepayer costs from being shifted to hyperscale data center infrastructure in West Louisville, with questions due by late August.
Cleveland Public Power Commissioner Ammon Danielson issued a June 25, 2025 letter supporting a proposed Slavic Village data center up to 125 MW while city officials debated grid capacity and permitting readiness.
Cleveland rejected a 150-megawatt Slavic Village data center and City Council considered a moratorium while H5 Data Centers pursued permits for a Cleveland expansion.
Seattle City Council introduced a one-year moratorium on new large-scale data centers, tied to Seattle City Light proposals, and scheduled committee votes for June 3.
5/21/2026 • Community & Local Opposition • General
The Columbus Dispatch / Victoria Moorwood, Haley BeMiller, Kelly Byer, Samantha Hendrickson, Maria DeVito65
Sunbury, Mount Orab, and Perry Township residents in Ohio organized moratoria and ballot proposals against Amazon-linked data center expansions, citing disclosure and local impact concerns.
5/17/2026 • Community & Local Opposition • General
Kentucky cities and counties imposed or considered data center moratoriums and zoning restrictions in August as proposed hyperscale projects prompted disputes over tax incentives and local impacts.
Legacy Investing proposed converting a former Star Tribune printing facility into a data center in Minneapolis's North Loop, drawing neighborhood scrutiny at a Wednesday meeting.
8/20/2026 • Community & Local Opposition • General
U.S. towns and states recorded more than 500 data center development bans in July as residents and officials challenged projects over power, water, noise, and pollution concerns.
8/10/2026 • Community & Local Opposition • General
U.S. jurisdictions, state officials, and community groups are delaying or restricting data center projects nationwide in 2025, threatening delivery of AI capacity.
8/10/2026 • Community & Local Opposition • General
Henderson County officials in North Carolina denied data-center permit activity for the vacant Coats America mill after residents raised rumors and sought moratorium-based options under state downzoning limits.
Alliance City Council is using an 18-month moratorium in Alliance, Ohio, to study data center impacts and establish zoning and operating conditions before permits resume.
Louisville Metro Council paused Dermody Properties' proposed 350,000-square-foot data center on Kramer Lane while reviewing new regulations in west Louisville.
AI data center developers and local governments are litigating bans and imposing project conditions across the United States over infrastructure, environmental, and land use impacts.
Louisville Metro residents and officials debated proposed data center zoning amendments and a six-month moratorium Wednesday at the University of Louisville Shelby campus.
Rubix Data Centers plans Ashland, Kentucky data centers while Russell, Boyd County, and Ashland moratoriums require lifting by August 31 for construction.
Jackson City Council will vote July 14 on a proposed 183-day moratorium on new data center applications amid zoning-law concerns and public opposition.
Eagan Capital sued the city of Eagan, Minnesota, in response to a February data center moratorium and asserted the measure overlaps with Minnesota Public Utilities Commission electrical regulation.
Inver Grove Heights City Council voted 3-2 in Minnesota to pause data center construction for one year, delaying a QLevr proposal on Carmen Avenue East.
Mayfield Village Council approved a one-year data center moratorium on June 22 in Ohio while staff study zoning, emissions, noise, and rapid-deployment risks.
Inver Grove Heights officials imposed a one-year pause on a proposed QLevr, LLC data center on March after a 3-2 vote amid neighborhood opposition and a litigation threat.
Inver Grove Heights, Minnesota, voted 3-2 for a one-year data center moratorium after residents raised environmental and grid concerns and a developer threatened a lawsuit.
6/26/2026 • Permitting & Regulation • General
KSTP.com 5 Eyewitness News / Sabrina Salguero Del Cid59
Inver Grove Heights, Minnesota, City Council approved a one-year data-center moratorium Friday, pausing a Carmen Avenue 50,000-square-foot proposal amid an environmental petition and threatened $150 million lawsuit.
Cleveland City Council will hold a hearing on a data-center moratorium this Thursday, guided by Cuyahoga County recommendations on zoning, energy, and water conditions.
Murray, Kentucky City Council initiated first reading of data center zoning amendments and set a July 16 public hearing after planning commission revisions.
Amazon employees in Seattle filed a civil rights complaint in June after public comments urging data center regulation, as Seattle City Council approved a one-year construction moratorium.
Louisville Metro Office of Planning presents a first draft of hyperscale data center regulations after a proposed moratorium, with public comments due July 10.
Louisville officials began public comment on proposed hyperscale data center zoning rules after a moratorium call following a Camp Ground Road approval classified as a telecommunications hotel.
Starbucks Center owners filed a conceptual plan with Seattle to assess a small data center at 2401 Utah Ave. S. amid a one-year moratorium on large projects over 20 megavolt-amperes.
Bowling Green City Commission approved new zoning rules for potential data center sites in Kentucky after a public hearing and a failed 3-2 six-month moratorium.
Asheville, North Carolina, advanced a proposed one-year moratorium on data center development after PEDE Committee approval and staff concerns about utilities, noise, heat, and zoning.
H5 Data Centers filed a $30 million permit for an expansion at 1625 Rockwell Ave. in Downtown Cleveland as City Council considered a data center moratorium.
Greenfield city councilors, led by Sarah Bolduc, review a one-year data center moratorium or special permit process to address electricity and water impacts.
Louisville Metro Planning Commission proposed hyperscale data center restrictions and industrial-only siting after initiating a 30-day public review period.
Amazon employees urged Seattle officials to pause data center permits and create rules on water and electricity transparency while the city council considered a moratorium.
Louisville Metro Council members Jennifer Chappell and Shameka Parrish-Wright propose a hyperscale data center moratorium after Rubbertown zoning-permit concerns surfaced during planning and zoning commission review.
Grove City, Ohio, approved a 6-1 one-year moratorium on new data center development on Monday after community hearings and a planned six-month impact study.
Cary, North Carolina officials considered a temporary data center moratorium on water-resource concerns tied to Jordan Lake at a Thursday-night council meeting.
St. Marys city councilors introduced a 12-month emergency moratorium on data centers while Ohio paused new data center tax exemptions during state committee review.
Inver Grove Heights, Minnesota, will consider a QLevr LLC data center application and a one-year moratorium after legal threats over zoning-law authority.
Charles Slife-led Cleveland proposal would pause data center permits while zoning rules for definitions, size, and utilities are updated as Lakeland Equity Group advances plans.
Greater Cleveland Partnership, backed by Ohio business and labor groups, urges Ohio communities to stop pausing data center permitting while lawmakers consider changing sales tax incentives.
Boardman, Ohio township trustees voted April 28 to impose a one-year moratorium on data centers while zoning and regulation options are developed amid community concerns.
Cleveland officials Blaine Griffin and Justin Bibb said no data centers will be sited at The Midline while pending legislation blocks new facilities until May 2027.
Painesville Township trustees approved a 12-month data center permit moratorium in Ohio to draft zoning language addressing power and water demand and related local quality-of-life concerns.
Reno City Council approved a 30-day moratorium on new data center conditional use permit applications while final moratorium details were scheduled for a June 1 vote.
Reno City Council imposed a 6:1 temporary moratorium on new data center applications starting June 1 while developing a longer-term permitting framework.
Minneapolis council member Aurin Chowdhury led a town hall Wednesday on a proposed moratorium on new data centers, with council review scheduled next Thursday and a June vote.
Cleveland denied a permit for Lakeland Equity Group’s proposed Slavic Village hyperscale data center on East 55th Street after local objections and a May 4 moratorium ordinance.
Cleveland rejected Lakeland Equity Group's incomplete building application for a proposed 150 MW Slavic Village data center campus while City Council considered a new data center moratorium.
Cleveland rejected a May 5 permit for a $1.6 billion hyperscale data center in Slavic Village, citing zoning review failure and residential siting concerns.
Inver Grove Heights, Minnesota city council approved a 3-2 one-year data center moratorium in response to a proposed Carmen Avenue project by Fortress Investment Group.
Seattle City Council drafted a one-year moratorium on new large data centers to address power-demand and electric bill concerns affecting Seattle residents.
Cleveland, Ohio filed due diligence discussions after a permit for a $1.6 billion hyperscale data center near Slavic Village drew concerns about power and water systems.
Black Mountain Town Council in Black Mountain, North Carolina adopted May 11, 2026 zoning amendments for data processing centers and requested drafting future moratorium language.
U.S. local governments are enacting more permanent data center moratoriums as community opposition grows over electricity costs, noise, and environmental impacts.
Sheboygan, Wisconsin, Common Council voted 7-3 in 2026 to forward a one-year moratorium draft limiting permits for data centers over 10,000 square feet to the Plan Commission.
Cleveland utilities committee voted for a three-month moratorium on standalone data center building permits, with a full council vote possible July 15.
Holly Springs approved a one-year data center moratorium on Tuesday, joining Wake, Chatham, Orange, and Durham pauses amid health, noise, and water concerns.
Cary Town Council debated a moratorium on new data center development during a meeting at Cary Town Hall on water and energy impact research tied to Jordan Lake.
Kentucky officials and policy analysts are challenging potential data center tax exemptions in Burgin and Hancock County during an August debate over local revenues.
Ohio residents and lawmakers in 2025 debate restrictions on new data centers after local zoning fights around Amazon-linked projects in Mount Orab, Perry Township, and Sunbury.
5/17/2026 • Community & Local Opposition • General
Mayor Justin Bibb and Cleveland officials rejected a 150 MW hyperscale data center proposal in Slavic Village and are considering zoning limits and a potential permit moratorium in Cleveland, Ohio.
5/27/2026 • Community & Local Opposition • General
Burgin residents challenged a proposed Panattoni Development data center and possible farmland annexation Tuesday at a city council meeting in Burgin, Kentucky.
8/13/2026 • Community & Local Opposition • General
Legacy Investing proposed converting Minneapolis' former Star Tribune printing facility into a data center while a city moratorium restricts large downtown facilities through November.
Residents in Burgin, Kentucky held a public meeting on July 20 ordinance consideration to oppose a proposed Mercer County data center near Shaker Village.
7/12/2026 • Community & Local Opposition • General
In Louisville, Rep. Morgan McGarvey opposed the Camp Ground Road hyperscale data center after Louisville Planning Commission approval, citing utility ratepayer and environmental concerns.
Inver Grove Heights, Minnesota, held a June 26 City Council vote to impose a one-year data center construction moratorium after residents requested an EAW environmental review for a QLevr proposal.
6/27/2026 • Community & Local Opposition • General
Seattle City Council on June 9 approved a moratorium on new data centers above 20 MVA after Amazon employees testified and later filed a Seattle Office for Civil Rights complaint alleging retaliation.
6/20/2026 • Community & Local Opposition • General
Amazon initiated HR investigations in Seattle in response to three employees' testimony supporting a one-year AI data center moratorium passed by the city.
6/19/2026 • Community & Local Opposition • General
In Kentucky, Breckinridge and Daviess counties adopted one-year data center moratoriums as Meade County rejected a proposal and Hancock County advances a TeraWulf site plan.
6/16/2026 • Community & Local Opposition • General
Nicole Bethel and Melissa Rexroth join Conserve Ohio to gather signatures in Springfield, Ohio, opposing a 75-megawatt Prime Ohio data center and supporting a constitutional mega-data center ban.
5/25/2026 • Community & Local Opposition • General
Grafton Village Council in Ohio voted May 19 for a five-year moratorium on data center development, alongside multiple Ohio state bills and an AG-approved amendment petition.
5/21/2026 • Community & Local Opposition • General
The Repository / Victoria Moorwood, Haley BeMiller, Kelly Byer, Samantha Hendrickson, Maria DeVito53
Ohio residents in Mount Orab, Perry Township, and Sunbury oppose proposed data centers, prompting local zoning moratoriums and state lawmakers to debate new restrictions.
5/17/2026 • Community & Local Opposition • General
Grove City Council approved a nine-month data center moratorium after residents protested a potential Stream Data Centers project in Ohio, with no applications submitted as of May 4.
5/11/2026 • Community & Local Opposition • General
Amazon investigated three AECJ-linked employees in Seattle during a civil rights dispute following testimony that supported a year-long AI data center moratorium.
6/19/2026 • Community & Local Opposition • General
Murray, Kentucky officials held first reading of a draft ordinance regulating potential data center development after Planning Commission edits and a one-week development moratorium, ahead of a July 16 public hearing.
Legacy Investing agreed in 2026 to purchase Minneapolis' former Star Tribune printing plant for a potential 20-megawatt data center redevelopment, pending city approval.
7/29/2026 • Infrastructure & Site Development • General
Rubix Data Centers proposed a 2-GW campus on the former AK Steel Ashland Works site near Ashland, Kentucky, as Russell considers lifting a temporary 180-day moratorium.
7/22/2026 • Infrastructure & Site Development • General
Mike DeWine announced an Ohio pause on tax incentives for new hyperscale AI data centers in 2025, while a referendum effort seeks a November statewide construction ban.
5/28/2026 • Project Finance & Incentives • General
Ohio Gov. Mike DeWine ordered a pause on new data center tax exemption requests during 2025 review by the Ohio General Assembly Joint Data Center Committee.
Gov. Mike DeWine ordered the Ohio Tax Credit Authority to freeze new data center sales-tax exemption requests in Ohio while a Joint Data Center Committee studies electric-intensive facilities.
5/27/2026 • Project Finance & Incentives • General
Raleigh Mayor Janet Cowell asked the Raleigh City Council to consider a six-month moratorium on large new data centers during an October review in Raleigh, North Carolina.
Seattle approved a year-long pause on large-scale data center construction on June 9 after Amazon employees testified, followed by internal investigations after a civil-rights complaint.
6/18/2026 • Community & Local Opposition • General
Amazon proposed a Manchester, Ohio data center as residents requested a pause over possible well-water contamination during stalled state regulation discussions in the Ohio Senate.
6/11/2026 • Community & Local Opposition • General
Jonathan Steirer discusses Cleveland's infrastructure readiness for hyperscale data centers after Cleveland denied the city's first hyperscale data center permit, citing transmission capacity and grid reliability constraints.
Jackson City Council approved an 183-day data center moratorium after Mississippi residents raised concerns about electricity, water, infrastructure costs, and community impacts.
Legacy Investing is acquiring the former Star Tribune printing plant in Minneapolis's North Loop to develop a data center under the city's downtown exemption.
7/31/2026 • Infrastructure & Site Development • General
Legacy Investing agreed to acquire Minneapolis's former Minnesota Star Tribune printing facility for a proposed data center conversion amid city restrictions and neighborhood concerns.
6/25/2026 • Infrastructure & Site Development • General
Kentucky Gov. Andy Beshear and Republican legislators are weighing repeal or reduction of statewide data center tax incentives before the 2026 legislative session in Kentucky.
8/31/2026 • Project Finance & Incentives • General
Kentucky Gov. Andy Beshear and state lawmakers are considering repealing or shortening data center tax incentives statewide ahead of the upcoming legislative session in Kentucky.
8/27/2026 • Project Finance & Incentives • General
Louisville Metro Planning Commission is scheduled Thursday to finalize proposed data-center zoning amendments after months of public opposition and a six-month moratorium.
Louisville opposition groups, state lawmakers, and local officials are contesting data-center incentives and zoning rules as the Planning Commission prepares amendments in Louisville, Kentucky, ahead of the 2026 elections.
Kentucky lawmakers and Louisville officials are reassessing data center incentives and development rules after rapid statewide project growth prompted a 180-day Louisville pause and anticipated 2027 legislative action.
Minneapolis City Council approved a six-month moratorium on new downtown data centers while zoning and scale rules are studied after public opposition at hearings.
Ohio officials and landowners discussed a deposit and build eminent domain proposal in Columbus, Ohio, as farmers feared expedited land taking for data center-related utility projects.
Ohio Governor Mike DeWine directed the Ohio Tax Credit Authority to pause new data center tax exemption requests while the Ohio General Assembly Joint Data Center Committee studies growth.
Save Ohio Parks, citing Ohio renewable-energy limits, urges Ohio policymakers to impose a moratorium on new data centers as AEP expects major load-driven generation growth.
Earlier this month in Kentucky, House Speaker David Osborne urged lawmakers to evaluate data center tax incentives as analysts warned of billions in potential costs.
8/31/2026 • Project Finance & Incentives • General