Türkiye, Canada Sign CANDU Plant Study Deal

Türkiye’s state-owned TUNAS and Canada’s AtkinsRéalis have agreed to study CANDU technology for a potential new nuclear power plant. Feasibility and front-end engineering work will assess site suitability, operations, costs, financing and Turkish industry participation before any investment decision. A six-unit, 4.5-gigawatt project is under discussion, but no final site or construction commitment has been announced.
If you read one thing
Reports the proposed plant’s discussed scale and possible timetable, while making clear that studies precede an investment decision.
Best explainer
Details the study’s scope, including financing, localization, workforce development and domestic industry participation.
The project remains at the assessment stage. A six-unit, 4.5-gigawatt plant and possible locations have been discussed, but the supplied coverage reports no final site selection or investment decision.
The agreement launches feasibility and front-end engineering studies, covering technical and commercial questions including site selection, CANDU adaptation, financing, economic viability, costs and risks.
AtkinsRéalis executives described discussions around a six-unit, 4.5-gigawatt project. The studies are expected to conclude by the end of 2027, with engineering design targeted for 2028 ahead of a final investment decision; these are reported plans, not completed milestones.
Sinop and Thrace are identified as potential locations for new nuclear plants, but coverage does not establish a selected site for this proposal. Türkiye’s stated target is 10 gigawatts of nuclear capacity by 2040.
6 units; 4.5 gigawatts
AtkinsRéalis said the parties were discussing a potential six-unit, 4.5-gigawatt plant; this is a plan under discussion, not an announced construction commitment.
By the end of 2027
AtkinsRéalis said its comprehensive feasibility study for the potential project was expected to be completed by the end of 2027.
By 2028
The engineering design study for the potential plant was expected to be completed by 2028, ahead of a final investment decision.
2036
AtkinsRéalis' nuclear president said first electricity from the proposed plant was expected in 2036.
10 gigawatts by 2040
Türkiye's stated target for total nuclear capacity, as reported by Reuters; it is a national target, not the capacity of the proposed plant.
11% by 2040
Türkiye expects nuclear power to meet 11% of electricity demand by 2040, according to the national energy plan as reported by Reuters.
4.8 gigawatts
Reported capacity of the Akkuyu nuclear plant under construction, which Türkiye is seeking to expand beyond.
Coverage on November 12 reported that Türkiye’s TUNAS and AtkinsRéalis had agreed to study CANDU technology for a possible new nuclear plant. Anadolu’s account, also carried by the master article, and Tasnim emphasized the planned feasibility and front-end engineering studies, including site, financing, costs, risks, local industry participation and workforce development. Reuters-based coverage in BNN Bloomberg and Ekathimerini added detail on a possible six-unit, 4.5-gigawatt project and projected study and design milestones. The reports described an assessment intended to inform investment decisions, not a final investment or construction commitment; they did not identify a selected site.