Öresundskraft Approves INNOZHERO Carbon Capture Project

Öresundskraft approved the final investment decision for INNOZHERO, a planned carbon capture and storage facility at the Filbornaverket waste-to-energy plant in Helsingborg. The project is designed to capture about 200,000 tonnes of fossil and biogenic CO2 annually for transport and permanent storage, with construction expected to begin toward the end of 2026. EU and Swedish public funding supports the project, which is projected to prevent nearly 1.9 million tonnes of greenhouse gas emissions over its first decade of operation.
If you read one thing
A clear overview of the investment decision, planned capture facility, funding and expected climate impact.
The evidence
The EU agency’s account details the project’s financing and planned capture, transport and storage arrangements.
The project has passed its final investment decision and is moving toward construction, but the coverage describes planned capacity and projected climate benefits rather than an operating facility.
Öresundskraft’s board approved the final investment decision on 30 September 2026; construction is expected to begin toward the end of 2026.
The planned capture facility is designed for about 200,000 tonnes of CO₂ per year, including fossil and biogenic emissions, for transport and permanent underground storage.
The project has EU Innovation Fund support of €54.1 million and Swedish Energy Agency support reported at about €22.8 million in total.
Coverage projects nearly 1.9 million tonnes of greenhouse gas emissions prevented over the first decade of operation; this remains a forecast, not a reported operating result.