Cadeler Wins Dogger Bank C Installation Deal

Cadeler has signed a firm contract to support turbine transportation and installation at Dogger Bank C, the 1.2 GW third phase of the Dogger Bank Wind Farm off eastern England. Its new Wind Apex vessel is scheduled to join the campaign in Q3 2027 and work alongside an existing installation vessel on the project’s 87 turbines.
If you read one thing
A clear overview of the firm contract, Wind Apex’s planned Q3 2027 deployment, and the 87-turbine campaign.
The evidence
Adds turbine model and capacity details, and reports that Dogger Bank C foundation installation was completed in 2025.
The installation support contract is firm, but Wind Apex’s deployment remains scheduled for Q3 2027; the supplied coverage does not establish that the campaign has begun.
Wind Apex is due to make its first deployment after delivery, joining Dogger Bank C’s turbine installation campaign in Q3 2027.
The vessel is contracted to add capacity alongside an existing installation vessel to support transportation and installation of Dogger Bank C’s 87 turbines.
Dogger Bank C is the third 1.2 GW phase of the wider 3.6 GW Dogger Bank Wind Farm; coverage says Wind Apex may also be deployed on other phases, but does not specify further assignments.