Last Update: 10/27/2026 at 5:34 AM EST

Virginia Data Center Regulation

Coverage from Hunton Andrews Kurth LLP, Roanoke Rambler, and others

Virginia Data Center Regulation topic image

Virginia’s approach to data-center development combines state policy, local siting decisions, and debate over the costs and impacts of large facilities.

The Data Center Accountability Framework and Executive Order 22 set out measures including local approval for facilities above 25 megawatts, limits on project secrecy and subsidies, and standards addressing water, energy, land use, noise, and backup power. They also address how grid costs are assigned to large customers. Some measures are described as proposals or requiring further legislative action, so the distinction between executive directives and provisions needing additional approval is important.

Key Articles4 of 58 articles

If you read one thing

The official overview introduces Executive Order 22 and the framework’s main policy areas, including disclosure and grid-cost responsibility.

Governor of Virginia

Best explainer

It clearly lays out the staged environmental requirements for emissions, cooling water, noise, and site assessments.

Hunton Andrews Kurth LLP / Katherine Kulbok, Gregory R. Wall, and Paul T. Nyffeler

The evidence

It distinguishes enacted review and disclosure requirements from broader proposals while explaining what Virginia’s law does not yet require.

Roanoke Rambler

The evidence

It adds specific reporting on the state’s grid-cost directive alongside the framework’s broader proposals.

Maryland Matters / Shannon Heckt
Key Issues

Local review is expanding, while statewide approval reform remains pending

Current law requires site assessments for certain facilities expected to use at least 100 MW, and counties are tightening or considering local review processes. The broader proposal to require local approval above 25 MW remains contingent on legislation, leaving approval pathways variable by locality.

Drawn from 4 articles

Environmental requirements are taking effect in stages

Tier 4-equivalent emissions limits apply to covered generator permit applications, and cooling-water requirements are being phased in for designated scarcity areas. Broader generator reviews and noise rules remain in agency work or rulemaking, so comprehensive statewide limits are not yet in place across these impacts.

Drawn from 4 articles

Grid-cost responsibility is shifting toward large-load customers

A State Corporation Commission directive calls for a Dominion tariff assigning data-center-specific transmission costs to those customers, and a large-load rate class is scheduled to take effect in January 2027. Broader state measures would allocate more transmission, generation, and PJM-related costs to the customers driving demand.

Drawn from 4 articles

Immediate rules limit agency secrecy and specified state assistance

Executive Order 22 bars executive-branch agencies from using NDAs that conceal material project information and ends specified discretionary site-readiness or expedited-permitting assistance for new projects at or above 25 MW. The NDA restriction does not itself cover local governments, while broader disclosure and approval reforms remain proposals.

Drawn from 4 articles

Key Numbers

25 megawatts

data center power use threshold for required local approval

any data center using more than this amount

“The broader framework would eliminate by-right approval and require local approval for any data center using more than 25 megawatts of power. It also gives communities tools to negotiate stronger agreements, ends state subsidies for data centers through Virginia’s site development programs, and removes future large data centers from the state’s fast-track permitting process.”

CBS 6 News Richmond WTVR and 1 other article

60% percent

required reduction in backup-generator emissions

Eligible projects receiving priority grid access

“The framework proposes limiting on-site natural-gas generation, closing emissions and Regional Greenhouse Gas Initiative payment loopholes, and prioritizing grid access for data centers that meet specified clean-energy and emissions conditions. Eligible projects would source clean energy five years faster than required by the Virginia Clean Economy Act, reduce backup-generator emissions by 60%, and keep on-site natural-gas generation to a de minimis level.”

Commonwealth of Virginia and 1 other article

more than 600 facilities

data centers already operating or under construction in Virginia

facilities largely outside the primary scope of the proposals

“Many proposals require legislative approval and would apply primarily to new data center applications, rather than the more than 600 facilities already operating or under construction in Virginia.”

Williamsburg Yorktown Daily and 1 other article

34 acres

planned campus area

Plaza 500 campus

“The Plaza 500 campus is planned on 34 acres off Edsall Road in Fairfax County, near Alexandria's western border and the Bren Mar neighborhood.”

Alexandria Brief

100 megawatts

projected electricity demand threshold

from a retail electric utility

“The law applies to a “high energy use facility,” defined as a facility the applicant reasonably anticipates will require at least 100 megawatts of electricity from a retail electric utility.”

Roanoke Rambler

Looking Back
101 Day Timeline
Jul 5Jul 26Aug 16Aug 30Sep 20Oct 11
The Story So Far
No material change

The new article reiterates Executive Order 22’s accountability framework and agency directives; it provides no evidence of a material change in implementation or effects since the prior state.

Previously

Virginia has begun statewide data center oversight through Executive Order 22, which directs agency action on disclosure, environmental impacts, water, noise, and grid costs. Broader proposals would expand local approval and operator obligations, but many measures still require regulations or 2027 legislation. County-level changes are also creating varied approval pathways.

History
10/09/2026

Loudoun and Prince William counties are changing local review processes, introducing varied approval pathways. However, the update still offers little evidence of completed statewide implementation or measurable effects.

All Articles58 articles
Important23 articles · CI Score 60 and above
Hunton Andrews Kurth LLP / Katherine Kulbok, Gregory R. Wall, and Paul T. Nyffeler
Virginia's General Assembly enacted data center reporting and environmental requirements in 2026 for facilities and utilities across Virginia.
9/21/2026 • Permitting & Regulation • General
Roanoke Rambler
Virginia lawmakers enacted Section 15.2-2209.5 on July 1, 2026, requiring local reviews of qualifying high-energy facilities before certain approvals statewide.
9/16/2026 • Permitting & Regulation • General
Code of Virginia
Virginia requires data-center permit applications submitted on or after July 1, 2026 to limit each engine-generator set to Tier 4 equivalent emissions.
7/5/2026 • Permitting & Regulation • General
Mondaq / K. Russell LaMotte, Jessalee L. Landfried, Nicole J. Waxman
Virginia Governor Abigail Spanberger signed Executive Order 22 on September 18, 2026, establishing a statewide data center accountability framework in Virginia.
10/13/2026 • Permitting & Regulation • General
Alexandria Brief / Ryan Belmore
On September 18, 2026, Gov. Abigail Spanberger proposed Virginia data-center oversight changes, while Fairfax County's Plaza 500 project continued toward Dominion Energy substation review.
9/18/2026 • Permitting & Regulation • General
The Piedmont Environmental Council / Don McCown
Piedmont Environmental Council is urging Orange County, Virginia, to pause new data center applications before an August 25, 2026, hearing on transmission-focused comprehensive-plan changes.
8/24/2026 • Permitting & Regulation • General
JD Supra / T. Preston Lloyd Jr., Christopher McDonald, Bradley Nowak
Virginia Governor Abigail Spanberger signed Executive Order 22 on September 18, 2026, establishing new disclosure, assistance, environmental, grid, and community requirements for large data centers statewide.
9/22/2026 • Permitting & Regulation • General
Blue Ridge Leader
Virginia Gov. Abigail Spanberger announced a data center accountability framework for Virginia on September 22, 2026, proposing stronger local review and environmental oversight.
9/22/2026 • Permitting & Regulation • General
America First Policy Institute
A regional policy brief sets out 18 options, with milestones extending from 2027 through 2030, to address data-center growth and related constraints in Virginia's 10th congressional district.
9/28/2026 • Power Procurement & Grid • General
Mondaq / David I. Schneider and Madeline Shay Williams
Virginia Gov. Abigail Spanberger signed Executive Order 22 on September 18, 2026, establishing statewide data center accountability and standardizing review across Virginia.
9/22/2026 • Permitting & Regulation • General
Colocation Scout
Virginia Governor Abigail Spanberger signed Executive Order 22 establishing a data center accountability framework on September 18, 2026, in Virginia.
10/1/2026 • Permitting & Regulation • General
Beveridge & Diamond / Russ LaMotte, Jessalee Landfried, Zach Pilchen, Dan Schulson, Nikki Waxman, Lia Crutchfield
Virginia Governor Abigail Spanberger signed Executive Order 22 on September 18, 2026, establishing statewide data center accountability measures in Virginia.
9/30/2026 • Permitting & Regulation • General
Maryland Matters / Shannon Heckt
Virginia Gov. Abigail Spanberger introduced a data center accountability framework ahead of the January legislative session to tighten project review and assign operators more infrastructure costs across Virginia.
9/25/2026 • Permitting & Regulation • General
McGuireWoods Consulting
Virginia Gov. Abigail Spanberger signed Executive Order 22 on Sept. 18, 2026, introducing statewide data center oversight measures as counties including Loudoun and Prince William tighten local approvals.
9/25/2026 • Permitting & Regulation • General
Union-Bulletin
Virginia Gov. Abigail Spanberger signed Executive Order 22 Friday in Norfolk, requiring local approval for data centers above 25 megawatts and directing new environmental standards statewide.
9/19/2026 • Permitting & Regulation • General
NBC Washington / Drew Wilder
Virginia Gov. Abigail Spanberger signed an executive order in Virginia establishing data center accountability measures covering disclosure, noise, backup generation, energy investment, and workforce opportunities.
9/18/2026 • Permitting & Regulation • General
Virginia Business / Kate Andrews
Virginia Gov. Abigail Spanberger signed an executive order in Virginia on September 18, 2026, proposing local approval, environmental standards, and energy restrictions for future large data centers.
9/18/2026 • Permitting & Regulation • General
FOX 5 DC
Virginia Gov. Abigail Spanberger signed a statewide data center accountability framework while Loudoun County supervisors advanced a proposed 12-month halt on new projects.
9/18/2026 • Permitting & Regulation • General
Virginia Mercury / Shannon Heckt
Virginia Gov. Abigail Spanberger introduced a data center regulatory framework and signed Executive Order 22 in Virginia on Friday, targeting permitting, environmental impacts, energy costs, and grid infrastructure.
9/18/2026 • Permitting & Regulation • General
CBS 6 News Richmond WTVR
Virginia Gov. Abigail Spanberger announced the Data Center Accountability Framework in Richmond, requiring stronger local, environmental, and grid oversight for large data centers.
9/18/2026 • Permitting & Regulation • General
WDBJ
Virginia Gov. Abigail Spanberger signed Executive Order 22 in Virginia to impose local, environmental, and grid-accountability requirements on large data center projects.
9/18/2026 • Permitting & Regulation • General
Venable / Kedrick Whitmore, Matthew J. Allman, Noah B. Klein, Zachary G. Williams
On September 18 in Virginia, Governor Abigail Spanberger issued Executive Order 22 directing state agencies to strengthen data center oversight and restrict specified state assistance for large-load projects.
9/24/2026 • Permitting & Regulation • General
The Register / Tobias Mann
Virginia Governor Abigail Spanberger established stricter datacenter oversight statewide, including local approval and environmental controls, after Loudoun County paused certain applications amid national community opposition.
9/18/2026 • Permitting & Regulation • General
Interesting16 articles · CI Score 45–59
WDBJ / Ben Wolf
Virginia Gov. Abigail Spanberger proposed data-center transparency and community benefits requirements after a nondisclosed potential project at Wood Haven Tech Park in Roanoke County.
9/19/2026 • Permitting & Regulation • General
Reuters
Virginia Governor Abigail Spanberger announced plans in Virginia on Friday to tighten data-center controls, ban nondisclosure agreements for large projects, and encourage renewable backup power.
9/18/2026 • Permitting & Regulation • General
WDBJ / Kaitlyn Kirkpatrick
Virginia Gov. Abigail Spanberger signed Executive Order 22 on Friday, imposing new data center environmental and local approval requirements across Virginia.
9/19/2026 • Permitting & Regulation • General
WSET / Craig Smith
Virginia Gov. Abigail Spanberger introduced a data center accountability framework in Richmond that would require local approval, limit subsidies, and impose stronger energy and environmental requirements.
9/18/2026 • Permitting & Regulation • General
Trinity Consultants
Virginia Governor Abigail Spanberger introduced a framework proposing stricter data center development, environmental, and energy requirements on September 18, 2026, in Virginia.
10/6/2026 • Permitting & Regulation • General
The Piedmont Environmental Council / Julie Bolthouse
On September 18 in Virginia, Governor Abigail Spanberger issued a data center accountability framework as the Piedmont Environmental Council renewed its call for a statewide development moratorium.
9/30/2026 • Community & Local Opposition • General
InsideNoVa / Megan Rhyne
Virginia residents and journalists are using FOIA and public meetings to investigate data center proposals and local government decisions across the state.
8/18/2026 • Community & Local Opposition • General
Cardinal News / Dwayne Yancey
Virginia Gov. Abigail Spanberger's executive order directs the state energy department to identify lower-impact data center sites across Virginia, with findings due by mid-March 2027.
9/24/2026 • Infrastructure & Site Development • General
Pilotonline / Dave Ress
At the annual Wilder Symposium in Richmond, Doug Wilder and Jim Gilmore criticized Gov. Abigail Spanberger's data-center policies over electricity, water, taxes, and transmission costs.
9/3/2026 • Policy & Utility Planning • General
Chamber of Progress / Adam Kovacevich
On September 18, Virginia Governor Abigail Spanberger issued a statewide executive order directing data center cost, environmental, community, and workforce measures in Virginia.
9/23/2026 • Policy & Utility Planning • General
WWBT
Virginia Gov. Abigail Spanberger signed an executive order establishing data center accountability rules statewide, including transparency requirements, local negotiation support, noise oversight, and backup-generator reviews.
9/18/2026 • Permitting & Regulation • General
Williamsburg Yorktown Daily / Craig Belcher
Virginia Governor Abigail Spanberger proposed data center regulations in Richmond covering permitting, water use, environmental impacts, and electricity infrastructure costs.
9/20/2026 • Policy & Utility Planning • General
Bay Journal / Lauren Hines-Acosta
Virginia Gov. Abigail Spanberger signed an order on Sept. 18 in Virginia establishing transparency measures and environmental protections for data center development.
9/18/2026 • Policy & Utility Planning • General
Chesapeake Bay Foundation
The Chesapeake Bay Foundation is urging Virginia, Pennsylvania, Maryland, and other Chesapeake-region policymakers to strengthen data center reporting and environmental protections as facility growth reaches 600 sites in 2025.
7/31/2026 • Policy & Utility Planning • General
Virginia LCV
Senator Mark Warner introduced a federal bill in Richmond, Virginia, to require data center environmental disclosure and tie tax benefits to conservation standards.
7/21/2026 • Policy & Utility Planning • General
The Piedmont Environmental Council
Piedmont Environmental Council urged Virginia officials to pause data center development statewide, citing oversight gaps, grid constraints, environmental risks, and community impacts.
9/18/2026 • Policy & Utility Planning • General
Additional19 articles · CI Score below 45
Commonwealth of Virginia
Virginia Governor Abigail Spanberger introduced a statewide data-center accountability framework to establish environmental, energy-cost, grid-reliability, and community-benefit requirements for operators.
10/3/2026 • Policy & Utility Planning • General
WHRO / Shannon Heckt
Virginia Gov. Abigail Spanberger introduced a data-center accountability framework on Sept. 18 that would expand environmental safeguards, local approvals and infrastructure cost responsibility statewide.
9/21/2026 • Policy & Utility Planning • General
InsideNoVa / Shannon Heckt
Virginia Gov. Abigail Spanberger introduced a data center accountability framework on September 18, 2026, to tighten permitting, environmental standards, and infrastructure cost allocation across Virginia.
9/20/2026 • Policy & Utility Planning • General
WAVY / SarahBeth Peterson
On Sept. 18 in Richmond, Virginia Gov. Abigail Spanberger unveiled a framework requiring greater local oversight and environmental accountability for large data centers.
9/19/2026 • Policy & Utility Planning • General
Fredericksburg Free Press / Jonathan Hunley
Virginia Gov. Abigail Spanberger announced a data-center accountability framework and signed Executive Order 22 in Richmond to tighten project approvals and allocate more grid costs to large facilities.
9/19/2026 • Policy & Utility Planning • General
Governor of Virginia
Virginia Governor Abigail Spanberger unveiled the Data Center Accountability Framework and issued Executive Order 22 on September 18, 2026, statewide in Virginia, targeting data center transparency, local approvals, utility costs, environmental impacts, and workforce standards.
9/18/2026 • Policy & Utility Planning • General
Cardinal News / Elizabeth Beyer
Virginia Gov. Abigail Spanberger introduced Executive Order 22 in Virginia on Friday to increase data center oversight and create an artificial intelligence task force.
9/18/2026 • Policy & Utility Planning • General
Virginia
Virginia Governor Abigail Spanberger introduced a data center accountability framework on September 18, 2026, requiring stronger permitting, environmental safeguards, and infrastructure cost responsibility statewide.
9/18/2026 • Policy & Utility Planning • General
Virginia Mercury / Shannon Heckt
Suhas Subramanyam and Mark Warner introduced federal proposals in Virginia to make data centers fund related grid infrastructure and disclose environmental impacts.
9/16/2026 • Policy & Utility Planning • General
GovTech
Virginia Gov. Abigail Spanberger announced new statewide data center rules requiring stronger local approvals, developer cost commitments and environmental safeguards across Virginia.
9/18/2026 • Policy & Utility Planning • General
News From The States / Shannon Heckt
Suhas Subramanyam and Mark Warner introduced federal data-center legislation addressing infrastructure costs, siting, environmental impacts, and security for Virginia's expanding industry.
9/16/2026 • Policy & Utility Planning • General
Virginia Chamber of Commerce
The Virginia Chamber of Commerce warned in Virginia that Governor Abigail Spanberger's proposed data center accountability framework could deter investment by restricting tax benefits, permitting flexibility, and confidential development discussions.
9/18/2026 • Policy & Utility Planning • General
Cardinal News
Virginia Gov. Abigail Spanberger's data center accountability framework drew industry support and environmental calls for an approval pause across Virginia.
9/18/2026 • Policy & Utility Planning • General
WCYB / Jaida Simone
Bert Mizusawa and Mark Warner are debating data center regulation and local control in Virginia during the state's U.S. Senate race before November.
8/9/2026 • Policy & Utility Planning • General
WRIC
Virginia Gov. Abigail Spanberger proposed data center regulation changes in Virginia, combining transparency requirements, infrastructure cost recovery, and environmental standards with an executive order on agency agreements and noise rules.
9/18/2026 • Policy & Utility Planning • General
Southern Environmental Law Center
Virginia Governor Abigail Spanberger announced in Richmond a data center reform framework addressing project transparency, energy costs, water consumption, and on-site gas generation.
9/18/2026 • Policy & Utility Planning • General
The Virginian-Pilot
In September in Virginia, Gov. Abigail Spanberger announced an accountability framework directing agencies to address the community, environmental, affordability, energy, and workforce effects of data center growth.
10/3/2026 • Policy & Utility Planning • General
WTOP News
Virginia Gov. Abigail Spanberger introduced a data center accountability framework in Virginia that would expand community oversight, restrict on-site power, and ban local-government nondisclosure agreements.
9/18/2026 • Policy & Utility Planning • General
WWBT / Shannon Heckt
Recently, U.S. Representative Suhas Subramanyam and U.S. Senator Mark Warner introduced Virginia-informed legislation requiring states to make data centers pay for dedicated energy infrastructure.
9/16/2026 • Policy & Utility Planning • General