Salem Pauses Verrus Data Center
Coverage from City of Salem, Salem Reporter, and others

Verrus has proposed a roughly $5.
1 billion, three-building data center campus on about 75 acres at Mill Creek Corporate Center in Salem, Oregon. The proposal has not received development approval, and Salem's September pause on development and construction gives the city time to assess local impacts as residents question the project's power and water needs, environmental effects, and the earlier confidential discussions. The dispute is also prompting Salem to consider changes to how it handles data center proposals and public engagement.
The biggest update is that Verrus’s Salem project is now framed as still early and unresolved, with no formal land-use or building approval yet, while the state land-sale fight has advanced to an actual termination order. Salem’s response also appears more organized, shifting from general concern to active consideration of new controls and policy tools.
The story has broadened from a single pending Salem campus review into a wider Oregon data center policy fight, driven by a governor-ordered land-sale cancellation and new municipal restrictions under consideration. At the same time, construction on Sabey’s Umatilla campus confirms the sector is still expanding even as Salem scrutiny intensifies.
- Oregon Gov. Tina Kotek canceled a state land sale tied to the Salem project.
- Salem is considering moratoriums, zoning changes, and NDA restrictions.
- Verrus’s project is now described as Oakline at Mill Creek on 75 acres.
- The Salem campus is framed at about $5.1 billion in planned investment.
- Sabey Data Centers has started construction in Umatilla.
The main change is that Verrus’s Salem project has moved from a general early-stage proposal into a more defined city review process, with hearings and planning scrutiny now explicitly underway. The story also narrows to this single Salem project and adds a clearer permitting and community-benefits framing around it.
The topic centers on two large proposed data center developments in Salem-area locations, led by Verrus in Salem, Oregon and by 4-3 Glen Brook Group in Salem Township, Pennsylvania. Both proposals are still at early stages and are tied to land use approvals, infrastructure constraints, and local review rather than final buildout decisions. Across the material, the main issues are power, water, site suitability, and how much economic benefit the projects would deliver in return for their scale.