Last Update: 09/22/2026 at 12:01 PM EST

Boulder City Tests Federal Data Center Approval

Coverage from Nevada Public Radio, KUNR, and others

Boulder City Tests Federal Data Center Approval topic image

The Townsite Data Center near Boulder City, Nevada, became a test of how federal agencies approve data centers on public land after BLM amended an earlier solar-project authorization for an 81-acre site.

Boulder City, environmental groups, and residents challenged the decision over local coordination, public participation, water use, and whether the existing environmental review was adequate. The Interior Board of Land Appeals later halted the approval, leaving the project’s planned 2027 construction and 2028 operations uncertain.

Key Articles4 of 28 articles

If you read one thing

It provides the clearest broad overview of the Townsite approval, Boulder City's challenge, and the underlying federal-local conflict.

Wyoming Public Media

Latest development

It captures the decisive appeals-board stay and explains why project-specific NEPA review is now the central constraint.

Engineering News-Record / Bryan Gottlieb

The counter-case

It presents the opposing position that BLM could rely on the existing solar review and amended federal authorization.

Boulder City Review / Alan Halaly

The evidence

It adds concrete evidence about cooling-water needs and the environmental differences between the data center and the solar project.

Nevada Current / Jeniffer Solis
Key Issues

Project-specific environmental review is now the central legal constraint

The Interior appeals board stayed BLM's approval after finding that the agency likely could not rely on the solar project's review for the materially different data center. Construction is paused while expedited proceedings and a broader environmental review move forward, although the stay is not a final rejection.

Strengthening

Drawn from 4 articles

Federal siting authority remains in conflict with local land-use control

Boulder City continues to argue that converting the solar-and-storage proposal into a data center required renewed local coordination and review, while BLM's federal-land approval bypassed the city's ordinary process. The stay has not resolved the underlying dispute over community authority.

Stable

Drawn from 4 articles

Water, power, and operational impacts distinguish the data center from the solar project

Opponents identify materially greater demands than those assessed for the solar proposal, including estimated construction water use of 560 acre-feet versus 25 acre-feet and electricity needs potentially several times Boulder City's existing load. Cooling and final water arrangements remain contested despite the developer's air-cooling plans.

Stable

Drawn from 4 articles

Townsite remains a precedent-setting test for federal data-center expansion

Townsite is testing whether federal agencies can accelerate data-center siting by modifying existing renewable-project approvals. The stay and likely requirement for project-specific review weaken the immediate replicability of that pathway while increasing the case's significance for other federal-land proposals.

Mixed

Drawn from 4 articles

Key Numbers

300,000-square-foot square feet

proposed data center size

He described the proposed 300,000-square-foot data center as a different project from the 19-MW solar facility.

Engineering News-Record

167-MW

planned data center capacity

Townsite Data Center

A federal appeals board halted approval Sept. 1 for the 167-MW Townsite Data Center on U.S. Bureau of Land Management property near Boulder City, Nev., finding that BLM likely violated the National Environmental Policy Act by relying on an environmental review prepared for a materially different, unbuilt solar project.

Engineering News-Record

19-MW

proposed solar facility capacity

project used as the environmental-review basis · 2023

BLM approved the data center in June without preparing a new or revised environmental assessment. It instead relied on a 2023 review of a proposed 19-MW solar facility and battery storage system at the same site.

Engineering News-Record

12 months

estimated solar-project construction duration

The board noted that the solar assessment estimated about 12 months of construction, while BLM estimated up to 18 months for the data center. Grouping both into a 12-to-18-month range, Gunter wrote, masked the potential for a 50% increase in construction impacts, including noise, dust, emissions and traffic.

Engineering News-Record

18 months

estimated data-center construction duration

up to

The board noted that the solar assessment estimated about 12 months of construction, while BLM estimated up to 18 months for the data center. Grouping both into a 12-to-18-month range, Gunter wrote, masked the potential for a 50% increase in construction impacts, including noise, dust, emissions and traffic.

Engineering News-Record

Contested Issue

Did BLM lawfully rely on the prior solar project's environmental review, or was a project-specific NEPA review required for the data center?

BLM determined that the data-center conversion was sufficiently similar to the previously reviewed solar project and approved it without a new assessment. Challengers and the Interior Board of Land Appeals characterized the data center as materially different, citing larger construction impacts and different water, pollution, habitat, and operating effects.

Existing review sufficient

3 articles · across 3 publications

The prior solar project's environmental review adequately covered the amended data-center use because BLM determined that the relevant impacts were not materially different.

Project-specific review required

3 articles · across 3 publications

The data center was not substantially the same as the solar project, so BLM likely violated NEPA by approving the conversion without a new, project-specific environmental review.

Could the data center proceed under the amended federal permit, or did the change from solar-and-storage use require a renewed local application and land-use review?

BLM authorized the data center by amending the existing federal solar-project authorization. Boulder City officials argued that replacing or adding the solar use with a data center materially changed the project and required a new application, renewed local review, and consideration of local land-use requirements.

Amended federal authorization

3 articles · across 3 publications

BLM could authorize the data center by amending the existing federal solar-project permit, allowing the project to proceed without restarting Boulder City's application process.

Renewed local review required

3 articles · across 3 publications

Adding a data center to the solar-and-battery proposal materially changed the project, requiring Townsite Solar 2 to restart its application and address local land-use requirements.

Looking Back
81 Day Timeline
Jun 15Jun 29Jul 13Aug 3Aug 17Aug 31
The Story So Far
No material change

The new articles reinforce that the Townsite Data Center remains halted while the NEPA challenge proceeds, adding detail about the board’s finding that the solar review understated the data center’s construction impacts but not materially changing the Topic’s status.

Previously

The Townsite Data Center, proposed on an 81-acre federal parcel near Boulder City, Nevada, was approved by the Bureau of Land Management after the agency determined that an earlier solar-project environmental assessment was adequate. Boulder City, environmental groups, and residents challenged the decision over local coordination, public participation, water use, and the scope of National Environmental Policy Act review; an Interior Department appeals judge later halted development while the challenge proceeds. The case could shape how quickly similar data centers are approved on federal land, particularly in water-constrained Western communities.

History
09/09/2026

The project is now more concretely characterized as a roughly $3 billion, 167-MW facility targeting construction in 2027 and operations in 2028, though the appeal has made that schedule uncertain.

09/02/2026

The dispute escalated from an unresolved appeal into an active legal halt: an Interior appeals judge suspended development after finding a persuasive potential NEPA violation. New water-use figures also sharpen the controversy, while a separate Colorado Springs approval broadens the regional context.

All Articles28 articles
Important24 articles · CI Score 60 and above
Nevada Public Radio / Yvette Fernandez
Boulder City officials planned an appeal and stay by July 27 after BLM approved the Townsite Data Center June 26 on federal land near Boulder City.
7/17/2026 • Permitting & Regulation • General
KUNR / Yvette Fernandez
Boulder City, Nevada plans an appeal and stay request by July 27 after Bureau of Land Management approved construction of the Townsite Data Center on BLM land near Eldorado Valley.
7/17/2026 • Permitting & Regulation • General
Wyoming Public Media
Boulder City, Nevada plans an appeal and stay by July 27 after BLM approved Townsite Data Center construction on June 26.
7/17/2026 • Permitting & Regulation • General
The Nevada Independent
Boulder City officials appeal a late-June BLM approval for Skylar Energy Resources' Townsite Solar 2 data center on federal land in Nevada.
7/16/2026 • Permitting & Regulation • General
Nevada Current / Jeniffer Solis
Boulder City Council appealed a Bureau of Land Management approval of the Townsite Data Center on Nevada federal land after objecting to environmental review reliance and lack of city consultation.
7/15/2026 • Permitting & Regulation • General
8 News Now
Boulder City officials approved an appeal in 2020s against a Town Site Solar 2 data center on nearby federal land after a Bureau of Land Management amendment bypassed local review.
7/14/2026 • Permitting & Regulation • General
KJZZ / Yvette Fernandez
Boulder City, Nevada, plans to appeal a June 26 BLM approval for Townsite Data Center on federal land amid concerns about consultation and environmental review.
7/28/2026 • Permitting & Regulation • General
Field & Stream / Travis Hall
The Bureau of Land Management approved Townsite Solar 2's 86-acre AI data center on federal land in Boulder City, Nevada, prompting local and environmental appeals.
8/10/2026 • Permitting & Regulation • General
Utah Public Radio / Yvette Fernandez
Boulder City filed a July 23 appeal with the Interior Board of Land Appeals challenging BLM approval of Townsite Solar 2's proposed data center in Boulder City, Nevada.
8/4/2026 • Permitting & Regulation • General
Sierra Club / Dana Drugmand
The Bureau of Land Management approved the Townsite Data Center on Nevada public land near Boulder City in June 2025, prompting environmental appeals.
8/3/2026 • Permitting & Regulation • General
Outside
The Bureau of Land Management approved Townsite Solar 2's 86-acre Townsite Data Center near Boulder City, Nevada, on June 26, 2026, while conservation groups and residents appealed the decision in July.
7/30/2026 • Permitting & Regulation • General
Hanford Sentinel
The Center for Biological Diversity, Sierra Club, and Boulder City appealed BLM's 2025 expedited approval of a federal-land data center in Boulder City, Nevada, seeking a construction stay.
7/28/2026 • Permitting & Regulation • General
Las Vegas Review-Journal / Alan Halaly
Center for Biological Diversity, Sierra Club, and Boulder City filed stay and appeal actions in Nevada challenging Bureau of Land Management expedited federal-land approval for a Townsite Solar 2 data center.
7/27/2026 • Permitting & Regulation • General
Boulder City Review / Alan Halaly
BLM approved Townsite Solar 2s Boulder City, Nevada data center on federal land by relying on an existing NEPA review, and Boulder City filed an appeal and stay request.
7/24/2026 • Permitting & Regulation • General
Las Vegas Review-Journal / Alan Halaly
BLM amended a 2023 solar permit to approve Townsite Solar 2s Boulder City data center on federal land in June 2025, and Boulder City Council appealed July 14.
7/19/2026 • Permitting & Regulation • General
Electrek / Michelle Lewis
The Bureau of Land Management approved Townsite Solar 2's 167-MW AI data center conversion on federal land near Boulder City, Nevada, on June 26, prompting a city appeal.
7/29/2026 • Permitting & Regulation • General
Engineering News-Record / Bryan Gottlieb
The Interior Board of Land Appeals halted BLM approval on September 1 for Townsite Solar 2 LLC's 167-MW data center near Boulder City, Nevada, citing likely NEPA violations.
9/3/2026 • Permitting & Regulation • General
Center for Biological Diversity
The Interior Board of Land Appeals halted the Townsite data center near Boulder City, Nevada, after environmental groups and residents challenged its approval without project-specific environmental review.
9/1/2026 • Permitting & Regulation • General
Common Dreams / Stephen Prager
The Interior Board of Land Appeals temporarily stopped the proposed Townsite Data Center near Boulder City, Nevada, after environmental groups and Boulder City challenged the Bureau of Land Management's environmental review.
9/1/2026 • Permitting & Regulation • General
Congresswoman Dina Titus
Following an administrative appeal, the Interior Department Board of Land Appeals halted a proposed BLM-land data center near Boulder City, Nevada, over potential National Environmental Policy Act violations.
9/1/2026 • Permitting & Regulation • General
8 News Now / Greg Haas
An Interior Department administrative judge halted the Townsite Solar 2 data center near Boulder City, Nevada, after finding potential deficiencies in the BLM environmental review.
9/1/2026 • Permitting & Regulation • General
Gazette / Alex Edwards and Brennen Kauffman
Integrity Matters and residents filed appeals challenging administrative approval for Raeden's Project Taurus AI data center in Colorado Springs, Colorado, before a Monday 5 p.m. deadline.
6/22/2026 • Permitting & Regulation • General
Spotlight PA / Mara Hoplamazian
The Bureau of Land Management approved a federal-land data center near Boulder City, Nevada, prompting a unanimous local appeal and broader opposition in July.
8/6/2026 • Community & Local Opposition • General
E&E News / Jason Plautz
Boulder City, Nevada, appealed a Bureau of Land Management decision approving a 167 MW data center on federal property, with the Interior Board of Land Appeals reviewing the challenge.
7/21/2026 • Community & Local Opposition • General
Interesting4 articles · CI Score 45–59
KKTV / Aspen Andrews
Colorado Springs Planning Commission voted 6-2 to deny appeals against Raeden's Project Taurus after a special hearing concluded shortly before midnight.
7/24/2026 • Permitting & Regulation • General
Utah Public Radio / Yvette Fernandez
Boulder City officials plan to appeal and seek a stay of the Bureau of Land Management approval for the Townsite Data Center, scheduled for submission by July 27.
7/22/2026 • Permitting & Regulation • General
KOAA News 5
Colorado Springs received five appeals Monday for a proposed Garden of the Gods Road data center, pending eligibility checks and planning commission review.
6/23/2026 • Permitting & Regulation • General
Datacenter Dynamics
Raeden received June 11 approval for a Development Plan Modification for 50MW Project Taurus in Colorado Springs, with local appeals due June 22, 2026.
6/15/2026 • Permitting & Regulation • General