Last Update: 10/15/2026 at 2:01 PM EST

Project Red Clay

Coverage from The American Prospect, AL.com, and others

Project Red Clay topic image

Project Red Clay is a proposed hyperscale data center campus by Cloverleaf Infrastructure in rural Lowndes County, near Hayneville, Alabama.

Plans described for the site include multiple large buildings and substantial electricity and water needs, bringing questions about utility capacity, water access, environmental effects, and local resources. County approvals and zoning authority, tax abatements, and residents’ requests for project records and clearer disclosure are also central to the project’s local impact. The debate reflects how a large industrial development can affect land use, public oversight, and the distribution of costs and benefits in its host community.

Looking Back
51 Day Timeline
Aug 25Sep 3Sep 12Sep 24Oct 3Oct 12
All Articles4 articles
Important2 articles · CI Score 60 and above
The American Prospect / Naomi Bethune and James Baratta
During ongoing local review, Cloverleaf Infrastructure is pursuing Project Red Clay, a proposed $1.5 billion hyperscale data center, while residents contest its water, tax, and disclosure plans in Lowndes County, Alabama.
10/1/2026 • Community & Local Opposition • General
AL.com / Hannah Denham
The Lowndes County Commission advanced a zoning process Monday in Lowndes County, Alabama, after residents challenged Cloverleaf Infrastructure's proposed Project Red Clay hyperscale campus.
8/26/2026 • Permitting & Regulation • General
Interesting2 articles · CI Score 45–59
Alabama Reflector / Anna Barrett
Lowndes County residents protested Project Red Clay at Monday's courthouse meeting, seeking records and zoning oversight for the planned 1,500-megawatt Alabama data center.
8/25/2026 • Community & Local Opposition • General
GovTech
Lowndes County commissioners approved more than $1.1 billion in tax abatements for Project Red Clay on Tuesday in Hayneville, Alabama.
10/14/2026 • Project Finance & Incentives • General