Oracle’s Project Jupiter data center in Doña Ana County, New Mexico is revising its planned power system after regulators rejected a natural-gas pipeline tied to the campus.
Oracle and developer BorderPlex Digital Assets have shifted from gas turbines and diesel generation toward Bloom Energy fuel cells, while also proposing closed-loop cooling and non-potable water use. The project’s scale, environmental impact, permit delays, legal challenges, and unresolved fuel supply create uncertainty around its cost, schedule, emissions, and ability to secure power.
Looking Back
103 Day Timeline
Articles published over time. Hover any bar for the period and its article count.
May 7
May 28
Jun 15
Jul 6
Jul 24
Aug 14
Sep 1
History
09/01/2026
The story now has a more concrete scale and schedule-risk profile: Project Jupiter’s massive power demand and investment are quantified, while the Green Chile pipeline target has slipped to February 2027. Opposition and permitting obstacles also appear more substantial, with thousands of comments, lawsuits, and a delayed air-quality hearing.
07/24/2026
The story has widened from a gas-pipeline fight into a more specific permitting and execution problem: Oracle is now revising Project Jupiter around fuel cells and closed-loop cooling while facing tighter regulatory review of air, land, and water approvals. OpenAI also appears as a project partner, sharpening the AI-infrastructure stakes.
Oracle and OpenAI develop Project Jupiter in Doña Ana County, New Mexico, using purchased water rights and closed-loop recycled non-potable water amid severe drought.
BorderPlex Digital Assets and Oracle revised Project Jupiter's microgrid for a Santa Teresa, New Mexico data-center campus to use fuel cells, after local disputes over water demand and air permits.
Energy Transfer delayed the Green Chile Project gas pipeline serving Oracle and OpenAI's Project Jupiter in southern New Mexico until February 2027 amid state land and environmental challenges.
Oracle filed a revised air permit for Project Jupiter in Doña Ana County, New Mexico, switching to Bloom Energy fuel cells and closed-loop cooling after community objections.
Transwestern Pipeline delayed the Green Chile Project to February 1, 2027, threatening Oracle's Project Jupiter data center development in Doña Ana County, New Mexico.
Oracle cancelled Project Jupiter's New Mexico natural gas plant in response to pipeline denials by FERC and the New Mexico State Land Office and will use Bloom Energy solid oxide fuel cells instead.
Oracle canceled a Project Jupiter natural-gas plant in New Mexico and shifted to Bloom Energy fuel cells after NMED permit withdrawals, regulator denials, and community scrutiny.
Oracle reported a second permit denial in New Mexico when state regulators rejected rights-of-way for a natural gas pipeline powering a planned data-center site.
GreenLatinos raised environmental justice objections in Doña Ana County, New Mexico, after BLM expedited a natural gas pipeline enabling Project Jupiter to proceed toward completion in August 2026.