Meta's Low-Water Idaho Launch
Coverage from Idaho Statesman, KBOI, and others

Meta has begun operating a $1.
2 billion data center in Kuna, Idaho, after a four-year build that included redesigns for AI infrastructure and liquid cooling. The facility uses a closed-loop cooling system that requires little or no cooling-related water for most of the year, while Meta has also supported 645 megawatts of renewable energy and more than $100 million in local water and wastewater improvements. The opening makes the site a major new customer for Idaho Power and expands Meta's data center presence in the Boise area.
Looking Back
2 Day Timeline
Sep 3
Sep 4
All Articles3 articles
Important
Meta began operating the Kuna Data Center in Kuna, Idaho, on September 3, 2026, after a four-year construction project supported by Idaho Power and three solar projects.
9/3/2026 • Water & Cooling • General
Meta opened its $1.2 billion AI data center in Kuna, Idaho, making the facility operational and potentially Idaho Power's largest customer.
9/3/2026 • Water & Cooling • General
Interesting
Meta began serving traffic from its AI-optimized data center in 2026 in Kuna, Idaho, following a $1.2 billion buildout with closed-loop cooling and renewable power.
9/4/2026 • Technology & Operations • General