Last Update: 09/30/2026 at 11:34 PM EST

Jupiter's Power Delays Pressure Project Financing

Coverage from Data Center Dynamics, Ars Technica, and others

Jupiter's Power Delays Pressure Project Financing topic image

Oracle's 1,400-acre Project Jupiter campus in Doña Ana County, New Mexico, faces power-supply and permitting delays, prompting Oracle to issue a force majeure notice as the planned 2028 opening comes under pressure.

After a proposed gas pipeline was blocked, plans have included fuel cells and a proposed 2 GW of new renewable energy; meanwhile, the roughly $18 billion project loan has reportedly been difficult to distribute and trades at a discount. The unresolved power and approval path adds execution and financing risk to a campus intended to provide AI computing capacity for OpenAI.

Key Articles4 of 6 articles

If you read one thing

This broad overview connects Project Jupiter’s financing pressure, power constraints, and local opposition.

Reuters / Harshita Mary Varghese

Best explainer

It explains Oracle’s renewable and fuel-cell plans as a response to the pipeline setback and power needs.

Data Center Dynamics / Zachary Skidmore

The evidence

It adds detail on the air-permitting pause and the emissions concerns behind local opposition.

Ars Technica / Jeremy Hsu

Latest development

It reports Oracle’s force majeure notice and links the potential schedule delay to lender exposure.

Yahoo Finance / Sridhar Natarajan, Brody Ford and Paula Seligson
Key Issues

Power supply remains a schedule constraint

Blocked pipeline access disrupted the original gas-turbine plan, and Oracle is now pursuing fuel cells and renewable procurement. Power delays have prompted a force majeure notice and put the planned opening timeline under pressure.

Drawn from 5 articles

Project financing is under pressure

The roughly $18 billion in project loans is reported to trade below par, while broader distribution has stalled and banks are holding more exposure than planned. Oracle’s delay notice has also drawn lender and investor scrutiny to how schedule risk and payment obligations are allocated.

Drawn from 3 articles

Permitting and local opposition add execution risk

Environmental and resident opposition over water and air quality has led to legal challenges, with a court pausing the air-quality permitting process. These approval and community concerns compound the project’s delivery risks.

Drawn from 3 articles

Key Numbers

89 to 91 cents on the dollar cents per dollar

quoted loan price

loans tied to the data center

“About $18 billion in loans tied to an Oracle-leased data center in New Mexico have come under pressure, with syndicate banks including Santander and Jefferies quoting the loans at 89 to 91 cents on the dollar, the Financial Times reported.”

Reuters and 1 other article

2031

target year for carbon-free energy matching

“Oracle’s commitment to achieve 100 percent carbon-free energy matching by 2031 would apply to renewable projects elsewhere in the state and would not directly eliminate emissions from the fuel cells.”

Ars Technica and 1 other article

about $3 billion USD

Blue Owl equity invested in Project Jupiter

“The program is being delayed by a year, according to a person familiar with Oracle’s notice and the deal. Blue Owl has about $3 billion of equity invested in the project and earns a lower return during construction, with returns increasing once the data center is completed.”

AOL

a year

delay to the Project Jupiter program

“The program is being delayed by a year, according to a person familiar with Oracle’s notice and the deal. Blue Owl has about $3 billion of equity invested in the project and earns a lower return during construction, with returns increasing once the data center is completed.”

AOL

$18 billion dollars

loans tied to the data center

Oracle-leased data center in New Mexico

“About $18 billion in loans tied to an Oracle-leased data center in New Mexico have come under pressure, with syndicate banks including Santander and Jefferies quoting the loans at 89 to 91 cents on the dollar, the Financial Times reported.”

Reuters

Looking Back
16 Day Timeline
Sep 9Sep 12Sep 15Sep 18Sep 21Sep 24
The Story So Far
No material change

No new articles were added, so there is no new evidence of a material change to Project Jupiter's power, permitting, or financing outlook.

Previously

Oracle's 1,400-acre Project Jupiter campus in Doña Ana County, New Mexico, faces power-supply and permitting delays, prompting Oracle to issue a force majeure notice as the planned 2028 opening comes under pressure. After a proposed gas pipeline was blocked, plans have included fuel cells and a proposed 2 GW of new renewable energy; meanwhile, the roughly $18 billion project loan has reportedly been difficult to distribute and trades at a discount. The unresolved power and approval path adds execution and financing risk to a campus intended to provide AI computing capacity for OpenAI.

All Articles6 articles
Interesting4 articles · CI Score 45–59
Data Center Dynamics / Zachary Skidmore
Oracle issued a New Mexico solicitation for 2GW of renewable generation to support Project Jupiter, its 2.5GW data center campus, after pipeline approval setbacks.
9/9/2026 • Power Procurement & Grid • General
Ars Technica / Jeremy Hsu
Oracle proposed about $2 billion in New Mexico renewable projects while Project Jupiter in Santa Teresa continues construction with natural-gas fuel cells amid lawsuits and a permitting pause.
9/11/2026 • Community & Local Opposition • General
Yahoo Finance / Sridhar Natarajan, Brody Ford and Paula Seligson
Oracle issued a force majeure notice concerning possible construction delays at Project Jupiter in southern New Mexico, where the 2.45-gigawatt campus is planned to open in 2028.
9/24/2026 • Project Finance & Incentives • General
AOL / Echo Wang, Isla Binnie, Sabrina Valle
Oracle issued a force majeure notice over power delays at Project Jupiter in New Mexico, prompting heightened financing scrutiny of AI data center projects.
9/24/2026 • Project Finance & Incentives • General
Additional2 articles · CI Score below 45
Reuters / Harshita Mary Varghese
Oracle's Project Jupiter data-center campus in Doña Ana County, New Mexico, faces discounted loans and local opposition after a proposed gas pipeline was blocked.
9/18/2026 • Project Finance & Incentives • General
AOL
Oracle's Project Jupiter data-center financing came under pressure in September as New Mexico opposition and a blocked gas pipeline threatened campus development in Doña Ana County.
9/18/2026 • Project Finance & Incentives • General