Last Update: 09/22/2026 at 11:34 PM EST
El Reno Leak Triggers Data Center Shutdown
Coverage from Data Center Dynamics, KOCO, and others

El Reno, Oklahoma, condemned an Athlon BT data center after a private water line released roughly 3 to 3.
8 million gallons, disrupting residential service and closing local schools for two days. City officials also cited dangerous structures, drainage problems, expired permits, a 2023 stop-work order, and the absence of a final certificate of occupancy. The facility cannot resume operations until violations are corrected, while the city considers recovering response and water-loss costs.
Looking Back
13 Day Timeline
Aug 28
Aug 30
Sep 1
Sep 3
Sep 5
Sep 7
Sep 9
All Articles3 articles
Important
El Reno, Oklahoma, condemned Athlon BT's Bitcoin mining data center after a private water-line failure released 3.8 million gallons, disrupted service, and exposed unresolved permitting violations.
9/9/2026 • Permitting & Regulation • General
El Reno officials issued safety and code notices to Athlon BT after the company mobile data center leaked three million gallons, disrupting schools and water service earlier this week.
8/28/2026 • Permitting & Regulation • General
El Reno officials issued emergency abatement and public nuisance notices after an Athlon BT data-center water line wasted more than 3 million gallons in El Reno during the week of August 28.
8/28/2026 • Water & Cooling • General