DTE Power for Michigan Data Centers
Coverage from The Detroit News, Planet Detroit, and others

DTE Energy’s service to Michigan data centers links long-term electricity contracts with decisions about capacity, grid investment, and the mix of resources used to supply large facilities.
Google’s Project Cannoli in Van Buren Township illustrates these arrangements: its 20-year contract includes minimum-use payments, while Google is to fund renewable generation and battery storage. Michigan regulators have also required safeguards intended to keep data-center costs from shifting to other DTE customers. The broader subject includes how DTE plans for rising demand, maintains reliable supply, and allocates the costs of new resources.
If you read one thing
It clearly explains the approved Google power agreement, its long-term obligations, new resources, and protections against shifting costs to other DTE customers.
Latest development
It extends the contract story to DTE’s proposed generation mix and projected additional data-center load, clarifying the broader capacity-planning challenge.
Long-term contracts with protections against cost shifting
Google’s DTE agreement commits the customer to long-term minimum payments and substantial obligations if it exits early. Regulatory conditions also require data-center costs to be tracked and paid by the developers rather than shifted to other DTE customers.
Resource additions meet a larger capacity-planning challenge
Google’s agreement funds substantial renewable generation and battery storage, while DTE’s broader plan proposes gas plants alongside nuclear, wind, and solar resources. DTE also reports discussions for additional data-center load, though whether that demand drives particular generation investments is disputed.
2.4 gigawatts
capacity of DTE’s two approved data center commitments
“Environmental groups worry that data center demand could drive fossil-fuel investment and shift costs to other ratepayers. Sierra Club organizer Bryan Smigielski noted that DTE’s two approved data center commitments total 2.4 gigawatts, while the proposed gas plants together would generate 2.1 gigawatts.”
5-1
Planning Commission vote tally
“The Van Buren Township Planning Commission voted 5-1 after public comment, completing a local approval process that began last year.”
2.1 gigawatts
combined generation capacity of the proposed gas plants
“Environmental groups worry that data center demand could drive fossil-fuel investment and shift costs to other ratepayers. Sierra Club organizer Bryan Smigielski noted that DTE’s two approved data center commitments total 2.4 gigawatts, while the proposed gas plants together would generate 2.1 gigawatts.”
$6.4 billion dollars
combined projected capital cost of the two proposed natural gas plants
“DTE’s latest long-range energy plan, filed in September, calls for two new natural gas plants, alongside expanded nuclear capacity and additional wind and solar. The company proposes opening one plant in Livingston County in 2031 and another in Monroe County in 2032. Their combined projected capital cost is $6.4 billion.”
1,600 megawatts
Renewable energy included in major grid additions
“Google’s planned server warehouse in Van Buren Township, near Detroit Metro Airport, will require 1 gigawatt of electricity—roughly as much power as 750,000 homes. Under the deal, Google will pay for major grid additions, including up to 1,600 megawatts of renewable energy such as solar and up to 480 megawatts of batteries.”
Google’s Van Buren data center clears final site-plan approval
Van Buren Township’s Planning Commission approved Google’s final site plan, advancing Project Cannoli beyond its previously established power-contract stage and making the proposed data-center load more concrete.
Previously
Michigan regulators approved long-term DTE power agreements for Google's proposed one-gigawatt Van Buren Township data center, with minimum-payment and cost-protection requirements. The project also ties new demand to renewable energy and battery storage. DTE reports further data-center power requests as its proposed generation expansion raises questions about reliability, emissions, and who pays for new capacity.