Missouri And Iowa Data Center Restrictions

Coverage from Washington Post, NDSU News, and others

Missouri And Iowa Data Center Restrictions topic image

Local governments in Missouri and Iowa are tightening or pausing data center development through zoning changes, moratoriums, and bans.

The most active pattern is precautionary local regulation driven by concerns about water use, utility strain, land use, and neighborhood impacts, alongside pushback from developers and business groups.

Looking Back
63 Day Timeline
May 19Jun 2Jun 9Jun 23Jun 30Jul 14
History
07/02/2026

The story has broadened from a handful of local moratorium debates into a more developed Missouri-Iowa regulatory push, anchored by St. Charles’ outright ban and St. Louis’ move toward a detailed siting framework. The new version also makes the conflict more concrete by adding named developers, utilities, and business groups pushing back against tighter local control.

06/29/2026

The story has sharpened from broad local resistance into more specific procedural moves: Dubuque County has formally imposed a one-year moratorium, Lee County is actively weighing its own pause and zoning rules, and St. Louis has delayed action while reconsidering thresholds and compliance timelines. The update also adds a new definitional fight over whether smaller bitcoin mining operations should be covered.

All Articles79 articles
Additional79 articles · CI Score below 45
Washington Post
A North Dakota coalition developed a model ordinance for data center siting after months of study, emphasizing electricity, water, environmental, and safety evaluations.
6/23/2026 • Permitting & Regulation • Local Approvals & Hearings
NDSU News
Applied Digital’s Ellendale, North Dakota project is cited alongside Williston to show how community outreach and power planning affect data-center disputes.
7/20/2026 • Community & Local Opposition • Public Engagement
KEYC / Evan Berg
Southcentral Minnesota Clean Energy Council holds a July 25 community event in Mankato, Minnesota to discuss data-center impacts during a year-long city moratorium.
7/20/2026 • Community & Local Opposition • Public Engagement
KTIV Siouxland's News Channel / Ryan Ricke
Salix, Iowa residents protested a proposed 900-acre data center on July 18, ahead of a City Council vote on a moratorium for new data centers.
7/18/2026 • Community & Local Opposition • Public Engagement
Times Republican
Iowa Citizens for Community Improvement says statewide residents are pushing for county moratoriums on new data centers due to water, energy, farmland, and subsidy impacts.
7/11/2026 • Community & Local Opposition • NIMBY Opposition
KPRC Click2Houston
Iowa Colony City Council will consider a July 20 resolution opposing data centers after Brazoria County adopted strict conditional development requirements addressing water, electricity, and community impacts.
7/18/2026 • Community & Local Opposition • NIMBY Opposition
KCRG / Keegan Turnbough
Dubuque County, Iowa held a first public town hall on a data-center ordinance in Peosta after a 12-month development halt, amid concerns about water quality and utilities.
6/24/2026 • Community & Local Opposition • Public Engagement
KCRG / Elizabeth Schultz
In Walford, Iowa, city leaders refused a proposed data-center annexation in April while Linn County added impact-study requirements and approved an 18-month moratorium.
7/3/2026 • Community & Local Opposition • Land Use Conflicts
TelegraphHerald.com
Dubuque County, Iowa officials prepared a 120-day moratorium on data center development after zoning meetings and petition-driven opposition near Dubuque Regional Airport.
5/22/2026 • Community & Local Opposition • Public Engagement
TelegraphHerald.com
Dubuque County supervisors in Iowa approved a 12-month moratorium on data center development applications and approvals after resident opposition during a special meeting Tuesday.
5/27/2026 • Community & Local Opposition • NIMBY Opposition
North Dakota Monitor / Jacob Orledge
A North Dakota legislative committee met in Bismarck on data centers and artificial intelligence, hearing residents request stronger zoning input and moratorium options amid electricity demand concerns.
7/15/2026 • Community & Local Opposition • Public Engagement
Wisconsin Public Radio
Superior, Wisconsin approved a one-year data center moratorium in 2024 while city officials study zoning and utility impacts after local concerns about health, water, and energy use.
6/17/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
KCRG / Keegan Turnbough
Karis contacted the City of Dubuque in preparation for a possible data center near Dubuque Regional Airport, but no application filed and county moratorium delays City Council action.
7/10/2026 • Water & Cooling • Water Supply & Access
WRAL
Durham County commissioners will vote after a public hearing on amending North Carolina Unified Development Ordinance rules to extend a data center moratorium to 12 months.
6/22/2026 • Permitting & Regulation • Local Approvals & Hearings
KGAN
Linn County, Iowa supervisors voted 2-1 to impose an 18-month moratorium on new data center development in unincorporated areas while newly adopted zoning water rules are evaluated.
7/1/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
KVLY / Devin Fry
Oliver County commissioners considered rezoning for Applied Digital's third North Dakota data center near Hanover and Center after signing a July 10 road-use agreement.
7/13/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
Inforum / Ken Sims
North Dakota cities and counties, with TechND and data-center industry input, developed a model ordinance in response to community concerns about data-center power, water, and environmental impacts.
6/19/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
KSDK
St. Louis advanced Board Bill 49 regulating large data centers, including siting distance, cool or green roofs, and 10-year renewable power, amid NAACP opposition and ongoing appeals of a Midtown 120-megawatt project.
7/8/2026 • Permitting & Regulation • Local Approvals & Hearings
InForum / Rob Port
Oliver County Commission approved Applied Digital’s data center building permit in central North Dakota, imposing conditions on water hauling, septic disposal, noise limits, traffic access, and a pending reclamation-bond solution.
7/13/2026 • Permitting & Regulation • Local Approvals & Hearings
Spectrum News St. Louis
St. Charles County Council introduced a six-month moratorium on large-scale data centers in Missouri while health and infrastructure impact studies are conducted.
6/30/2026 • Permitting & Regulation • Local Approvals & Hearings
The Portland Press Herald
Brunswick Maine approved a 180-day moratorium on 1 MW-plus data center permitting after Gov. Janet Mills vetoed a statewide restriction bill.
6/2/2026 • Permitting & Regulation • Local Approvals & Hearings
inewsource / Philip Salata
Imperial County supervisors imposed a 45-day urgency ordinance moratorium on data center projects after community opposition and pending an ad hoc committee report.
6/17/2026 • Permitting & Regulation • Local Approvals & Hearings
Linn County Iowa
Linn County, Iowa Board approves an 18-month moratorium on EU-3 rezoning applications for large-scale data centers in unincorporated areas, effective immediately.
7/1/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
Linn County Iowa
Linn County, Iowa, approved a moratorium effective immediately through January 1, 2028 on EU-3 large-scale data center rezoning applications in unincorporated areas.
7/1/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
St. Louis Magazine
Miriam Keller and the St. Louis Planning Commission advanced stricter city data center regulations on Wednesday, including lower megawatt thresholds and a 50 percent renewable requirement at operation.
6/11/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
St. Louis Public Radio / Kavahn Mansouri
St. Louis aldermen advanced amendments to Board Bill 49 for data center zoning after contentious debate over renewable-energy waivers and land-use exemptions.
7/20/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
Oshkosh Northwestern
Winnebago County, Wisconsin, proposed a 12-month moratorium on hyperscale AI data center permitting after concerns about power demand, water use, and local infrastructure strain.
6/17/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
St. Louis Public Radio
July 29 Board of Adjustment appeals will review conditional approval for a 120-megawatt data center planned for the former Famous-Barr warehouse in Midtown St. Louis.
7/9/2026 • Permitting & Regulation • Local Approvals & Hearings
Dane County Legistar
The Advisory Committee on Data Centers met in Dane County, Wisconsin on June 9, 2026 to consider a moratorium on zoning permit applications for data center siting.
6/9/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
CBS News Atlanta / Jamal Goss
DeKalb County commissioners extended a data center application moratorium by 100 days through end-of-September after resident requests for additional health, environmental, and water studies.
6/10/2026 • Permitting & Regulation • Local Approvals & Hearings
Daily Gate
Lee County supervisors in Iowa discussed seeking legal counsel for a possible six-month moratorium on new data center construction during a Tuesday work session.
6/14/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
Boone County / Sean Horan
Boone County commissioners in Indiana approved a one-year moratorium on new unincorporated data center development on June 15, 2026 to reassess land use and infrastructure impacts.
6/15/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
City of Desert Hot Springs
Desert Hot Springs City Council holds a public hearing on extending a moratorium on data center licensing, permitting, and entitlements in California.
7/3/2026 • Permitting & Regulation • Local Approvals & Hearings
Spencer Fane / Connor Walsh
St. Louis City approved a conditional use permit for a data center at The Armory on April 21, 2026 after rejecting a data center moratorium and advancing zoning regulations in 2025-2026.
6/24/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
Mankato Free Press
North Mankato, Minnesota, City Council will consider a 12-month moratorium on new data centers after months of community debate over water and energy impacts.
7/5/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
KEYC / Kate Jones
Mankato City Council approved a one-year moratorium on data centers and high-impact utility consumers on July 13 while staff study local zoning, water, and health impacts.
7/14/2026 • Permitting & Regulation • Local Approvals & Hearings
STLPR
St. Louis aldermen advanced amended data-center zoning rules on July committee action Tuesday, with added water, energy, and noise conditions prompting developer and environmental group disputes.
7/7/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
STLPR
St. Louis Planning Commission delayed a data center zoning rules vote in Midtown, Missouri, after public comment and proposed changes to megawatt thresholds and renewable energy timelines.
5/19/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
STLPR
St. Charles, Missouri city council voted 7-1 on Aug. 14 to make a data center moratorium permanent by disallowing data centers under city zoning.
5/20/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
STLPR
St. Louis Planning Commission sent finalized data-center zoning rules to the Board of Aldermen after public comment and amendments addressing siting, size limits, and renewable energy requirements.
6/11/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
City of Dubuque
Dubuque, Iowa scheduled two July public input meetings and a resident survey to help shape a future data center ordinance.
7/2/2026 • Permitting & Regulation • Local Approvals & Hearings
Mississippi Today / Katherine Lin
Jackson, Mississippi held a public forum on a northwest Jackson data-center rezoning request, with Saxum rescheduling a Planning Board hearing for June 24.
6/12/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
Mississippi Today
Jackson, Mississippi held a public hearing on data center development while drafting regulations that would block approvals until rules are finalized, after a rezoning request in northwest Jackson.
6/23/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
Times Republican / Robert Maharry
Marshalltown, Iowa, Planning and Zoning Commission scheduled work sessions, a community roundtable, and public hearings to develop data-center zoning rules after a four-month moratorium.
7/18/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
KSHB 41 Kansas City News / Tod Palmer
Independence, Missouri approved a 180-day moratorium on new data centers and BESS projects after resident pressure, excluding ongoing Nebius and Patmos applications.
7/9/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
Spectrum News St. Louis
St. Charles, Missouri city council approved a 7-1 ordinance amendment on May 19 banning data center proposals.
5/20/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
KMOV4
St. Charles city council voted 7-1 to permanently ban new data center construction on Tuesday night using zoning-based permitting and conditional use prohibitions.
5/20/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
KMOV4 / Cory Stark
A Las Vegas developer seeks final city approval for a 120 MW Midtown St. Louis data center after conditional use permitting and resident concerns over water, air, noise, and power grid impacts.
5/20/2026 • Permitting & Regulation • Local Approvals & Hearings
Spectrum News Maine
Brunswick and Scarborough, Maine approved 180-day moratoriums on data center construction as councils evaluate ordinance changes and residents raise water and electricity concerns.
6/8/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
KTIV Siouxland's News Channel / Joe McMahan
Plymouth County supervisors approved a one-year revocable moratorium on data center and industrial battery storage construction in Iowa on Tuesday, citing rulemaking needs for water, power, and noise.
6/17/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
KMTV 3 News Now Omaha
Mayor Jill Shudak sought a up to one-year moratorium on new data center projects in Council Bluffs, Iowa, to review infrastructure and ordinances amid water and power concerns.
6/19/2026 • Permitting & Regulation • Local Approvals & Hearings
KTIV / Sophie Wyckoff
Sioux County Board of Supervisors planned an informational session on a Hull, Iowa data center proposal after a one-year moratorium on new data centers.
6/28/2026 • Permitting & Regulation • Local Approvals & Hearings
KTIV / Kaylie Dahms
PathOne Data Centers and Sunstone Investments appeared before Sioux County supervisors in Iowa in response to a new data center moratorium after stating an end user was secured before the pause.
6/30/2026 • Permitting & Regulation • Local Approvals & Hearings
WKMG News 6 & ClickOrlando
Seminole County commissioners discussed a potential data center moratorium in Florida, citing a county code review and new July 1 authority for regulating large load customers.
6/25/2026 • Permitting & Regulation • Local Approvals & Hearings
Spectrum News St. Louis
St. Charles County Council in Missouri introduced a six-month moratorium on large-scale data center proposals and expansions to conduct local impact studies.
6/30/2026 • Permitting & Regulation • Local Approvals & Hearings
Iowa Public Radio
Woodbury County, Iowa, plans a one-year moratorium for unincorporated-area data center projects after resident opposition to a MidAmerican Energy site considered for development near Salix.
6/17/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
WisPolitics / Joshua Irvine
Dane County Executive Melissa Agard signed an 18-month moratorium on hyperscale data centers in Wisconsin after unanimous county board approval.
6/9/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
Telegraph Herald
Scott Nelson criticized Dubuque County's one-year data center development moratorium as legally weak after supervisors voted to pause projects while drafting an ordinance.
6/24/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
Telegraph Herald
Dubuque County considers data center rules in 2024 as a 420-acre site near Dubuque Regional Airport faces airport hazard-zone zoning requirements.
7/12/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
KCRG
Dubuque County, Iowa approved a 12-month data center moratorium on Tuesday to draft zoning rules amid resident concerns and city water-connection review requirements.
5/26/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
KCRG / Libbie Randall
Cedar Rapids Mayor Tiffany O'Donnell announced a third data center planned for 1515 33rd Ave. SW, following Linn County large-data-center moratorium actions.
7/8/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
KCRG / Keegan Turnbough
Dubuque County supervisors agreed to seek county attorney permission to hire a consultant to explore a data center ban while the zoning ordinance moves forward, after airport and economic impact presentations.
7/14/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
Green Bay Press-Gazette
Brown County, Wisconsin committee members on June 2 declined a proposed countywide moratorium on data centers, citing lack of zoning authority over independent municipal rules.
6/3/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
Radio Iowa / Sheila Brummer
Woodbury County, Iowa supervisors planned a one-year data center moratorium after Salix annexed farmland, while MidAmerican Energy confirmed a potential site under consideration within Salix limits.
6/17/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
Radio Iowa / Lindsay Kruse
Ida County Board of Supervisors voted in late June to impose an indefinite moratorium on new data center development in Iowa.
7/13/2026 • Permitting & Regulation • Local Approvals & Hearings
WLBT / Anthony Warren
Saxum Investment Group LLC asked Jackson Planning Board to postpone a rezoning vote for about 190 acres on Forest Avenue until June 24.
5/26/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
TelegraphHerald.com
Dubuque County Zoning Commission recommended a moratorium on new data-center development to county supervisors after large resident turnout and opposition at a Tuesday meeting.
5/20/2026 • Permitting & Regulation • Permitting & Regulation: Zoning & Land Use
KOTA / Ryan Hill
Sequitor Edge plans a 15-MW data center at Black Hills Industrial Center in Rapid City while South Dakota drought and heat increase summer power load demands.
7/2/2026 • Power Procurement & Grid • Load Growth & Capacity
TelegraphHerald.com
Jason White and Dubuque County Board of Supervisors candidates discussed July 13, 2026 data center economic forecasts for Dubuque County, Iowa.
7/17/2026 • Market Demand & Investment • Project Valuation & Returns
InForum / Sav Kelly
In Bismarck, North Dakota lawmakers and Tony Clark discussed 2030 electricity-use projections for AI data centers and concerns about grid capacity and cost allocation.
7/15/2026 • Policy & Utility Planning • Policy & Utility Planning: Utility Resource Planning
Valley News Live / Harrison Pray
Barnes County, North Dakota imposed a six-month moratorium on new data centers due to power and transparency concerns raised by Valley City officials.
5/26/2026 • Policy & Utility Planning • Policy & Utility Planning: Utility Resource Planning
News Dakota
Barnes County commissioners in North Dakota imposed a six-month moratorium on new data centers as officials cited electric transmission and generation constraints and unresolved transparency and siting coordination issues.
5/27/2026 • Policy & Utility Planning • Policy & Utility Planning: Utility Resource Planning
South Dakota Searchlight / Jordan Lamb
Jordan Lamb, CEO of Oahe Electric Cooperative, argues South Dakota should enable data-center growth by aligning permitting and grid upgrades to planned load growth.
6/19/2026 • Policy & Utility Planning • Policy & Utility Planning: Utility Resource Planning
The Gazette / Fern Alling
Oppidan plans a 10-megawatt Cedar Rapids data center at 1515 33rd Ave. SW, using closed-loop cooling and Alliant Energy power, with construction starting in late fall or early spring.
7/10/2026 • Infrastructure & Site Development • Construction & Buildout
Times Republican
A former Marshall County development director urges Marshalltown, Iowa to delay a two-year data center moratorium and instead coordinate with Alliant Energy and Marshalltown Water Works.
6/22/2026 • Policy & Utility Planning • Policy & Utility Planning: Utility Resource Planning
WLBT
Jackson, Mississippi officials used open-records documents to outline a Lake Hico hyperscale data center recruitment plan involving Entergy coordination and local ordinance work.
7/17/2026 • Infrastructure & Site Development • Infrastructure & Site Development: Land Acquisition & Site Selection
TelegraphHerald.com
Karis sought hundreds of acres near Dubuque Regional Airport in Dubuque County, Iowa, with May 15 emails to zoning administrator Ben Kober amid local moratorium debate.
6/26/2026 • Infrastructure & Site Development • Infrastructure & Site Development: Land Acquisition & Site Selection
North Dakota Monitor / Amy Dalrymple and Michael Achterling
North Dakota lawmakers announced an interim Artificial Intelligence and Data Center Committee to study data center water and electricity impacts and AI regulation ahead of the 2027 legislative session.
6/25/2026 • Policy & Utility Planning • Infrastructure Siting Policy
North Dakota Monitor
Warrey will lead a North Dakota interim committee studying data centers, water and electricity impacts, and AI regulation ahead of the January 2027 session.
6/26/2026 • Policy & Utility Planning • State Energy Policy