U.S. Grid-Scale Battery StorageU.S. Grid-Scale Battery StorageCoverage from Facilities Dive, Utility Dive, and others
00/00/0000
DailyWeekly
U.
S. grid-scale battery storage spans utility projects, solar-plus-storage facilities, corporate power contracts, and the technologies needed to provide capacity beyond periods of sunlight. One example is Mammoth Solar in West Virginia, where MN8 Energy, Google, and Eos Energy Enterprises plan to combine 86 megawatts of solar with lithium-ion and zinc-based long-duration storage on a reclaimed coal mine. Such developments connect renewable generation to regional grids such as PJM while supporting data centers and other large electricity users. The subject also includes manufacturing support and the broader question of how storage can make clean power more dependable.
Looking Back
19 Day Timeline
Articles published over time. Hover any bar for the period and its article count.
Sep 2
Sep 5
Sep 8
Sep 11
Sep 14
Sep 17
Sep 20
History
10/05/2026
Developers now quantify the project’s prospective local economic benefits at about $350 million in investment and 200 construction jobs; these remain estimates.
Google, MN8 Energy, and Eos Energy Enterprises will develop a solar-and-storage project in West Virginia from 2028 to support data centers and regional PJM capacity.
Google will procure power from MN8 Energy's Mammoth Solar project in West Virginia, combining solar and 350 MWh of storage for regional data centers from 2028 onward.
Google and Cypress Creek Energy are developing a potential 2.5-gigawatt solar and 2.9-gigawatt-hour storage project in Mississippi County, Arkansas, for completion by 2029.
Equinor subsidiary East Point Energy has placed the 100-megawatt Citrus Flatts battery storage facility into commercial operation in southern Texas, supporting wind balancing and wholesale market trading.
Google, esVolta, Quintrace, and LevelTen Energy completed a three-month United States pilot using batteries and hourly certificates to shift solar supply into higher-demand periods.
Google, MN8 Energy, and Eos Energy Enterprises are developing an 86-megawatt solar project with lithium and zinc storage in Kanawha County, West Virginia, for operation from 2028 through 2030.
Google, MN8 Energy and Eos Energy Enterprises announced a planned 86-megawatt solar and battery project in Kanawha County, West Virginia, for operation in 2028.
Quintrace, esVolta, and LevelTen Energy completed a three-month Google-sponsored pilot that shifted 9.2 GWh of solar energy through batteries at United States projects.
Quintrace, esVolta, LevelTen Energy, and Google completed a three-month United States pilot using hourly certificates to verify battery-shifted renewable energy.
Google, MN8 Energy, and Eos Energy Enterprises are developing a 436 MWh solar-and-storage project in Kanawha County, West Virginia, with operations beginning in 2028.
SMT Energy and FlexGen began operating the Houston IV battery facility in Houston, Texas, in 2024, adding 160 megawatts of storage capacity to the ERCOT grid.
East Point Energy is operating a 100-megawatt lithium-ion battery facility in Harlingen, Texas, to support grid reliability as electricity demand rises.
SMT Energy, FlexGen Power Systems, and Irby Construction commissioned a 160-MW battery storage facility in Houston, Texas, on September 9, 2026, supporting ERCOT during rising demand.
SMT Energy, FlexGen, and Irby Construction commissioned the 160-MW SMT Houston IV battery storage facility in six weeks in Houston, Texas, supporting the ERCOT grid.
Zeo Energy and Fulcrum Point Holdings announced a storage and solar development collaboration in Utah to reduce gas consumption and emissions while supporting reliable commercial power.
Seven States Power Corporation issued a procurement request in Tennessee for 220 megawatts of distribution-connected batteries with three utility partners, targeting construction in 2027.
Google, Quintrace, esVolta, and LevelTen Energy completed a three-month pilot using hourly renewable certificates to verify battery storage dispatch and clean energy delivery.
Georgia Power placed the 128-MW Robins Battery Facility into commercial operation near Warner Robins, Georgia, to store solar energy and support peak-demand grid reliability.
St. Christopher Episcopal Church, Google, MN8 Energy and Eos Energy Enterprises are advancing solar and battery projects in West Virginia as federal incentives and PJM grid conditions shape deployment.
MN8 Energy, Google, and Eos Energy Enterprises announced a planned 86 MW solar and 350 MWh storage project in Kanawha County, West Virginia, to supply dispatchable clean power to the PJM grid from 2028.
Google, esVolta, Quintrace, and LevelTen Energy completed a three-month United States pilot using batteries to shift solar electricity and hourly renewable attributes during demand gaps.
9/18/2026 • Markets & Industry & Innovation • General
Eos Energy Enterprises received an $87 million Department of Energy loan advance on September 15 for its Thorn Hill zinc battery facility in Warrendale, Pennsylvania.
East Point Energy began commercial operations at the 100 MW Citrus Flatts battery facility in Harlingen, Texas, expanding Equinor's merchant storage portfolio in ERCOT.
East Point Energy began commercial operation of the 100 MW Citrus Flatts battery in Harlingen, Texas, providing renewable balancing and ancillary services across ERCOT.
MN8 Energy and Google announced plans for a $350 million solar and battery storage facility in Cannelton, West Virginia, with construction scheduled for 2027.
MN8 Energy, Eos Energy Enterprises, and Google announced a planned solar and storage facility in Kanawha County, West Virginia, with operations scheduled to begin in 2028.
MN8 Energy, Google, and Eos Energy Enterprises announced a West Virginia project combining 86 MW of solar with 380 MWh of storage for dispatchable clean power on the PJM grid.
MN8 Energy, Google, and Eos Energy Enterprises announced a West Virginia solar-and-storage project that will supply Google's regional data centers through the PJM grid from 2028.
MN8 Energy, Google, and Eos Energy Enterprises announced a planned 86 MW solar and 380 MWh storage project in Kanawha County, West Virginia, for the PJM grid.
Georgia Power began commercial operation of the 128-megawatt Robins Battery Facility near Warner Robins, Georgia, to shift solar electricity during peak demand.
Equinor’s East Point Energy began commercial operation of the 100 MW Citrus Flatts battery in Harlingen, Texas, adding flexible capacity to the ERCOT grid.
East Point Energy, an Equinor company, started commercial operations at the 100 MW/200 MWh Citrus Flatts battery facility in Harlingen, Texas, strengthening ERCOT energy storage capacity.