Last Update: 09/17/2026 at 11:34 PM EST

Data Centers Push PJM Toward Emergency Measures

Coverage from Scranton Times-Tribune, Cincinnati Enquirer, and others

Data Centers Push PJM Toward Emergency Measures topic image

Rapid data center growth is adding pressure to the PJM power system, with extreme heat exposing limited reserves, transmission constraints, and sharp wholesale price increases.

In response, the U.S. Department of Energy has repeatedly authorized PJM to direct large customers to use backup generation during emergencies, while PJM and utilities prepare for further demand growth. The response is also intensifying disputes over transmission costs, customer tariffs, emissions, and the extent to which data centers should provide or fund their own power capacity.

Key Articles5 of 74 articles

If you read one thing

PJM Heat Emergency Exposes Grid Strain From Data Center Load Growth

It gives the clearest broad overview of how heat, data-center demand, emergency grid actions, and power prices are converging in PJM.

Bloomberg / Naureen S. Malik

Best explainer

PJM Auction Caps Prices as Data Center Demand Widens Reserve Gap

It explains the capacity shortfall, rising demand, and proposed procurement reforms driving PJM's reliability challenge.

Utility Dive

Latest development

Pennsylvania PUC Gets New Data Center Grid and Cost Duties

It captures the latest validated Pennsylvania rules shifting forecasting, curtailment, reporting, and grid costs toward large-load customers.

Altoona Mirror

The evidence

Why Data Center Load Behavior Requires New Grid Reliability Rules

It shows why synchronized data-center load changes are becoming a distinct reliability problem requiring new operating standards.

Utility Dive / Brandon Owens

The counter-case

Maryland OPC Challenges PJM’s 7,000-MW Data Center Power Plan

It presents the ratepayer-protection case against shifting uncertain data-center procurement costs onto existing customers.

Maryland Office of People's Counsel
Key Issues

PJM capacity is tightening while costs rise

Data-center demand continues to outpace near-term resource additions: PJM's latest capacity auction reached its price cap while remaining about 6.8 GW below its reliability target. Data centers are driving a substantial share of capacity and wholesale-cost exposure for other customers.

Drawn from 6 articles

Backup generation is a short-term reliability tool

Federal emergency authorizations allow PJM to direct data centers and other large loads toward onsite generation or curtailment during severe heat and reserve stress. The tool provides rapid flexibility but remains constrained by emissions, health, noise, and operating concerns; reported events generally did not require forced data-center disconnection.

Drawn from 6 articles

Data-center load behavior is becoming a reliability variable

The Ashburn disturbance demonstrated that hyperscale facilities can shed more than 3 GW and transfer to backup power within seconds, producing measurable grid imbalance even without a reported reliability impact. Operators and regulators are moving toward better telemetry, modeling, recovery requirements, and enforceable computational-load standards.

Drawn from 4 articles

Regulators are shifting obligations toward large-load developers

Pennsylvania is assigning more forecasting, curtailment, reporting, interconnection, and potential reliability-procurement obligations to large data centers, while Ohio proposals similarly emphasize self-supplied generation and developer-funded grid connections. Consumer advocates and other stakeholders continue to contest whether PJM-wide costs should instead be borne by existing customers.

Strengthening

Drawn from 6 articles

Key Numbers

four substations

new substations needed to connect the campus

new high-voltage connection infrastructure

The project also says it will pay the full $4.2 billion cost of the new high-voltage transmission lines and four substations needed to connect the campus to the regional system.

Cincinnati Enquirer

six months

maximum period for utilities to complete interconnection studies

The tariff is intended to help utilities account for how large-load customers affect consumer costs, infrastructure and reliability. It makes large customers responsible for infrastructure and connection costs, requires financial deposits and collateral, and requires utilities to complete interconnection studies within six months.

Altoona Mirror

$10 to $20 dollars per month

potential increase in some Ohio household electric bills

some Ohio households

Data center demand may already be adding $10 to $20 a month to some Ohio household electric bills, yet utilities and regulators cannot tell customers exactly how much or why.

Cincinnati Enquirer

10 gigawatts

planned new generation

PORTS-Pike campus

It is expected to provide roughly eight gigawatts of computing power and plans approximately 10 gigawatts of new generation—enough, if used by homes instead, to serve about 8 million households.

Cincinnati Enquirer

$4.2 billion USD

cost of new high-voltage transmission lines and four substations

project says it will pay the full cost

The project also says it will pay the full $4.2 billion cost of the new high-voltage transmission lines and four substations needed to connect the campus to the regional system.

Cincinnati Enquirer

Contested Issue

Should data centers directly bear the incremental capacity, transmission, and interconnection costs associated with their electricity demand?

State regulators, utilities, and industry advocates are pursuing tariffs and procurement mechanisms that assign infrastructure and reliability costs to large-load customers, while consumer advocates argue that PJM backstop and transmission plans could shift uncertain or excessive costs onto existing residential and industrial ratepayers.

Large-load cost responsibility

3 articles · across 3 publications

Data centers and other new large loads should pay for the generation, capacity procurement, transmission, and interconnection upgrades they cause or require.

Ratepayer-protection concerns

3 articles · across 3 publications

PJM-wide or long-term backstop and transmission procurement should not place uncertain data-center-driven costs on existing residential and industrial customers; such plans should be rejected, narrowed, or made contingent on customer commitments.

Looking Back
121 Day Timeline
May 7May 28Jun 25Jul 16Aug 13Sep 3
The Story So Far
Broadening

State rules expand data-center accountability to costs, curtailment, and self-supply

Pennsylvania is formalizing large-load obligations through customer-funded infrastructure, demand forecasting, potential priority curtailment, usage reporting, and possible charges for PJM backstop capacity. In Ohio, the PORTS-Pike proposal illustrates a self-supply model in which a hyperscale campus would develop roughly 10 gigawatts of generation and fund $4.2 billion in grid connections, while potential household cost impacts remain disputed.

Previously

Rapid data-center expansion is tightening PJM's capacity and transmission margins, exposing new reliability risks during heat, raising power costs, and pushing utilities and regulators toward emergency flexibility and developer-funded infrastructure.

History
09/08/2026

The response has moved from proposed emergency flexibility toward repeated federal authorizations allowing PJM to direct qualifying data centers onto onsite generation. Disputes over cost allocation and tariffs have also become more concrete, with named Maryland and Ohio stakeholders challenging who pays for grid upgrades.

08/29/2026

The story has shifted from projected data-center pressure and regulatory disputes to demonstrated operational stress, including a major Ashburn load-transfer incident and a capacity-auction shortfall. Regulators and utilities are also moving from debate toward assigning more grid-upgrade obligations directly to large-load customers.

All Articles74 articles
Important31 articles · CI Score 60 and above
Scranton Times-Tribune / Frank Lesnefsky
DOE authorized PJM during a heat wave to require data centers across multiple states, including Pennsylvania, to use backup generators with permitting waivers for reliability.
7/15/2026 • Power Procurement & Grid • General
Cincinnati Enquirer / Dennis Doyle
Ohio utilities and regulators are evaluating how expanding data centers, including PORTS-Pike in Pike County and an Amazon Web Services proposal near Trenton, could affect electricity costs and grid infrastructure.
9/4/2026 • Power Procurement & Grid • General
Utility Dive
Monitoring Analytics asked FERC to require Mara Holdings to keep Long Ridge generation in PJM markets if the agency approves the proposed $1.5 billion sale tied to growing data center load.
6/1/2026 • Power Procurement & Grid • General
Utility Dive
DOE issued an emergency Federal Power Act section 202(c) order for PJM Interconnection to curtail backup-equipped large loads for three hot-weather days starting May 18 in Maryland and Virginia.
5/19/2026 • Power Procurement & Grid • General
Data Center Dynamics / Ruslan Seyidov
The US Department of Energy authorized PJM Interconnection on July 14, 2026, to direct eligible backup resources at large-load sites during Level 3 emergencies in the PJM region.
8/16/2026 • Power Procurement & Grid • General
AOL
Monitoring Analytics and PJM reported data-center-driven demand raising PJM capacity charges in the June 2028 to May 2029 auction while PJM sought backstop procurement for reliability shortfalls.
7/15/2026 • Power Procurement & Grid • General
The Philadelphia Inquirer
PJM released annual auction results on June 30, projecting $6.3 billion in added electricity costs over three years driven by data-center peak power demand across 13 Eastern states and DC.
7/15/2026 • Power Procurement & Grid • General
Prince William Times / Peter Cary
On July 2, PJM Interconnection issued emergency alerts during a heat wave but did not order power cuts to data centers in Northern Virginia, avoiding planned generator-based contingency.
7/3/2026 • Power Procurement & Grid • General
The Columbus Dispatch
DOE approved PJM Interconnection emergency authority from July 1 to July 3 to direct data centers and other large users to backup generators during record heat-driven demand in Ohio.
7/2/2026 • Power Procurement & Grid • General
Gibson Dunn
DOE issued Emergency Order No. 202-26-23 on May 18, 2026, enabling PJM to direct data-center backup generation during Level 3 alerts in the PJM region.
5/21/2026 • Power Procurement & Grid • General
Watts Up With That
PJM released a white paper proposing reliability-focused power market design changes as large-load data centers expand across its US territory.
5/10/2026 • Power Procurement & Grid • General
Wattsupwiththat
PJM Interconnection said grid strain from data center demand and delayed generation additions requires market design changes that may curtail power to new large-load customers during peaks.
5/10/2026 • Power Procurement & Grid • General
Tom's Hardware / Jowi Morales
Maryland’s Office of People’s Counsel filed a FERC complaint against PJM Interconnection over transmission cost allocation tied to projected data center load growth.
5/9/2026 • Power Procurement & Grid • General
WTOP News / Scott Gelman
PJM and regional utilities reported record July peak demand during extreme heat, while demand-response and backup-generation arrangements were cited as limiting brownout risk.
7/15/2026 • Power Procurement & Grid • General
Bloomberg / Naureen S. Malik
PJM issued emergency load management and maximum generation alerts during extreme East Coast heat, while DOE authorized PJM backup generation at data centers.
5/18/2026 • Power Procurement & Grid • General
Reuters
PJM issued emergency demand-response orders during a heat wave to prevent outages as transmission congestion and generator outages reduced reserve margins in the Mid-Atlantic and Midwest.
7/3/2026 • Power Procurement & Grid • General
Utility Dive
Joseph Bowring of Monitoring Analytics reported data centers caused 38% of PJM Interconnection's latest capacity auction charges and urged a FERC-filed September backstop auction.
7/20/2026 • Power Procurement & Grid • General
WJLA / Tom Roussey
PJM and Dominion Energy managed a sudden 3,000-megawatt data-center disconnection after an Ashburn transmission fault, while PJM and NERC develop reliability standards.
7/28/2026 • Power Procurement & Grid • General
Maryland Office of People's Counsel
Maryland's Office of People's Counsel and allied state advocates asked FERC in August to reject PJM's proposed 7,000-megawatt Reliability Backstop Procurement for data center demand.
8/21/2026 • Power Procurement & Grid • General
E&E News / Benjamin Storrow
PJM, SPP, and ERCOT experienced record or near-record July demand during extreme heat, with data center growth intensifying grid planning pressures across the United States.
8/4/2026 • Power Procurement & Grid • General
Spotlight PA / Mara Hoplamazian
The Energy Department has authorized PJM Interconnection and Southwest Power Pool since May to direct data centers and other large users onto backup generation during regional heat emergencies.
7/31/2026 • Power Procurement & Grid • General
Bloomberg
PJM and other U.S. ISOs issued emergency grid alerts as data centers and broader demand growth tightened power reserves during hot, humid weather.
7/27/2026 • Power Procurement & Grid • General
RTO Insider / Michael Brooks
PJM reported a reliability imbalance after a Northern Virginia transmission line fault caused about 3 GW of data center load to drop between 7:55 and 8:00 a.m.
7/23/2026 • Power Procurement & Grid • General
Data Center Knowledge / Shane Snider
Dominion Energy and PJM reported that an Ashburn, Virginia transmission fault triggered more than 3 GW of hyperscale data center load to disconnect and transfer to backup power within seconds.
7/23/2026 • Power Procurement & Grid • General
The Jersey Vindicator / Krystal Knapp
Monitoring Analytics quantified data centers as a major driver of PJM capacity charges while PJM missed reliability targets despite maximum-price capacity auctions.
7/20/2026 • Power Procurement & Grid • General
NBC4
PJM Interconnection reported a 6.8-gigawatt capacity shortfall in its latest auction for the second year, prompting Ohio lawmakers to advance bills addressing data-center driven electricity costs and forecast scrutiny.
7/20/2026 • Power Procurement & Grid • General
Politico / Ariel Wittenberg
DOE approved a PJM Interconnection request to potentially require Virginia data centers to run backup diesel generators during extreme-heat demand peaks.
7/1/2026 • Power Procurement & Grid • General
Yahoo / Khac Phu Nguyen
Federal and state officials scheduled July 23 talks on PJM reforms as AI-driven data center load growth raises PJM prices and capacity costs.
6/4/2026 • Power Procurement & Grid • General
Utility Dive
PJM's independent market monitor reported on August 24 that data center load contributed materially to higher wholesale prices and capacity revenues during the first seven months of 2026.
8/27/2026 • Power Procurement & Grid • General
OilPrice.com
PJM Interconnection reported a 2028/2029 capacity auction shortfall and plans a September FERC backstop procurement as Virginia data center load grows.
7/15/2026 • Power Procurement & Grid • General
Utility Dive
PJM stakeholders approved a reliability backstop procurement plan for a near-term capacity shortfall, targeting FERC review and a September auction to support data-center load growth.
7/2/2026 • Power Procurement & Grid • General
Interesting40 articles · CI Score 45–59
New Jersey Monitor / Christine Condon
PJM Interconnection and the Trump administration authorized emergency measures during an extreme heatwave, requiring data centers to activate backup generation through July 3.
7/1/2026 • Power Procurement & Grid • General
The Wall Street Journal / Jennifer Hiller
Ting Labs said about 3 GW of Data Center Alley demand in northern Virginia disconnected Wednesday, destabilizing the power grid for several minutes.
7/24/2026 • Power Procurement & Grid • General
Reuters
Belden Brick reported higher capacity charges in Sugarcreek, Ohio as PJM capacity prices surged in 2025, driven by regional data-center electricity demand growth.
7/7/2026 • Policy & Utility Planning • General
Reuters
PJM Interconnection forecasts record peak electricity demand during a heat wave as data-center growth increases congestion and reserve costs, while QTS withdraws a Virginia project filing.
7/2/2026 • Policy & Utility Planning • General
Bloomberg Law
FERC plans a July 23 technical conference with PJM to resolve tariff and jurisdiction responsibilities for data center load growth under the Federal Power Act.
6/22/2026 • Policy & Utility Planning • General
Cincinnati Enquirer
In Ohio, PUCO approved an AEP Ohio data center tariff in July 2025 as residents and advocates debate PJM grid strain and rising electricity bills.
5/17/2026 • Policy & Utility Planning • General
Utility Dive
PJM Interconnection reported a 2028-2029 capacity auction clearing at the 325 per MW-day cap as data centers increased forecast demand and reserve adequacy shortfalls persisted.
7/15/2026 • Policy & Utility Planning • General
Utility Dive
Eighty Maryland state lawmakers backed a May 7 FERC complaint arguing PJM transmission cost allocation for data-center-serving projects shifts costs to Maryland ratepayers, with comments due July 27.
6/18/2026 • Policy & Utility Planning • General
Utility Dive
FERCs December 2025 order to PJM adds non-firm interconnection and dedicated on-site generation pathways as PJM forecasts 30 GW of new demand by 2030.
6/9/2026 • Policy & Utility Planning • General
Utility Dive
PJM advanced a backstop reliability auction from March to September and urged member states to define auction cost allocation for new data center loads.
5/20/2026 • Policy & Utility Planning • General
Babst Calland / Kate Cooper
Pennsylvania regulators and PJM Interconnection moved in 2025 to shift power, grid-upgrade, and reliability risks for large AI data centers toward developers statewide.
8/14/2026 • Policy & Utility Planning • General
Maryland Office of People's Counsel
Maryland Office of People’s Counsel, joined by consumer advocates from Ohio, Delaware, and Illinois, sought FERC clarification in 2026 on PJM data-center transmission cost allocation.
7/17/2026 • Policy & Utility Planning • General
Fox Business
PJM Interconnection expects Thursday demand of about 166,147 MW and gained emergency authority to curtail data center and backup-generator load if needed.
7/2/2026 • Policy & Utility Planning • General
Dayton Daily News
Ohio Manufacturers Association told PUCO of Ohio that AES Ohio data center tariff terms could leave other customers exposed to transmission upgrade costs.
6/27/2026 • Policy & Utility Planning • General
Babst Calland
On May 27 and May 13, 2026, Pennsylvania issued GRID standards and a PUC model tariff for large-load data centers while PJM reported capacity-market scarcity pressures.
5/29/2026 • Policy & Utility Planning • General
Tom's Hardware / Jowi Morales
Monitoring Analytics warned PJM Interconnection that data center load is driving higher wholesale and capacity costs ahead of the June 2026 base residual auction.
5/16/2026 • Policy & Utility Planning • General
Maryland Office of People's Counsel
Maryland People''s Counsel David Lapp urged PJM in Baltimore to exclude projected data center load growth from markets and transmission planning after an OPC filing at FERC challenged Maryland transmission cost assignment rules.
5/14/2026 • Policy & Utility Planning • General
US News
Maryland governor Wes Moore pushed PJM Interconnection reforms on May 11, proposing long-term contracts and added data-center cost responsibility as capacity prices surged.
5/11/2026 • Policy & Utility Planning • General
Maryland Office of People's Counsel
Maryland Office of People's Counsel filed an FERC complaint in 2026 contesting PJM hybrid transmission cost allocation rules that allocate data-center-driven grid costs to Maryland ratepayers.
5/7/2026 • Policy & Utility Planning • General
Utility Dive / Brandon Owens
PJM reported that a July 22, 2026 transmission disturbance in Northern Virginia caused data centers to transfer more than 3 GW to backup power within minutes.
8/25/2026 • Policy & Utility Planning • General
OilPrice.com
During a heat dome, the U.S. Department of Energy issued a 2026 emergency order enabling PJM to direct large data centers toward onsite backup generators to protect grid capacity.
7/3/2026 • Policy & Utility Planning • General
Gizmodo / Bruce Gil
U.S. Energy Department authorized PJM to require data centers to use onsite backup power during an extreme heat wave across 13 states and Washington, D.C.
7/2/2026 • Power Procurement & Grid • General
Spectrum News 1 Ohio
Ohio data center expansion is increasing electricity demand across PJM Interconnection, prompting curtailment actions and consideration of temporary hyperscale disconnections during peak conditions.
8/27/2026 • Power Procurement & Grid • General
Yahoo Finance / John Ainger
PJM Interconnection faced record power demand during July 2 heat, as AI data center load intensified grid reliability stress across multiple US RTO regions.
7/26/2026 • Power Procurement & Grid • General
Maryland Matters / Christine Condon
PJM Interconnection received a U.S. Department of Energy emergency order on an ongoing heatwave to require backup generators through July 3, affecting AI data centers.
6/30/2026 • Power Procurement & Grid • General
Maryland Matters / Christine Condon
PJM Interconnection requested U.S. Department of Energy emergency authority to require data centers to use backup generators during a Maryland heat wave through Friday.
6/29/2026 • Policy & Utility Planning • General
Reuters / Tim McLaughlin
PJM Interconnection proposed requiring data centers across its territory from Washington, D.C., to Chicago to use backup generation during future grid emergencies.
8/13/2026 • Policy & Utility Planning • General
Reuters
PJM Interconnection reported near-capacity-auction record pricing around $325 per megawatt-day in a reliability-shortfall year driven by rising data-center power demand.
7/14/2026 • Policy & Utility Planning • General
NBC10 Philadelphia / Ali Ingersoll
PJM proposed Monday a large-load registry for data centers and other facilities across its 13-state region to prioritize electricity reductions during shortages.
7/30/2026 • Policy & Utility Planning • General
AOL / Tim McLaughlin
Dominion Energy and PJM reported a transmission line outage in northern Virginia caused over 3 GW of data center load to drop offline on Wednesday, with backup power transfer and voltage disturbances extending to Chicago.
7/23/2026 • Policy & Utility Planning • General
ARLnow
Senator Mark Warner backed the Power for the People Act in response to Virginia electricity price impacts from data-center growth tied to PJM reliability and utility cost allocation.
6/3/2026 • Policy & Utility Planning • General
E&E News by POLITICO / Christa Marshall
Monitoring Analytics reported sharp PJM wholesale price and capacity cost increases in the first quarter, citing AI data center load that tightens supply and stresses planning.
5/15/2026 • Policy & Utility Planning • General
Common Dreams
Maryland People's Counsel filed a FERC complaint against PJM Interconnection over transmission cost allocation for data-center driven load growth.
5/8/2026 • Policy & Utility Planning • General
Environment America
DOE Secretary Chris Wright approved PJM air pollution standard exemptions for data centers using backup power during July 1-3 amid extreme heat.
7/4/2026 • Policy & Utility Planning • General
Al Jazeera / Andy Hirschfeld
PJM Interconnection requested DOE action during a US heatwave after lawmakers and communities raised concerns about AI data center power and water strain.
7/3/2026 • Policy & Utility Planning • General
Conduit Street Blog / Dominic Butchko
Eighty bipartisan Maryland lawmakers urged FERC to limit transmission cost pass-through tied to out-of-state data center demand, citing projected $2 billion in higher Maryland bills.
6/22/2026 • Policy & Utility Planning • General
The Daily Record
Maryland enacted the Utility RELIEF Act in 2026, requiring data centers to register with the Public Service Commission and pay for grid connection upgrades.
6/15/2026 • Policy & Utility Planning • General
CNS Maryland
Maryland candidates linked higher residential electric bills to data center load growth and supported the Utility RELIEF Act signed in May, with costs and grid upgrades targeted to developers.
6/5/2026 • Policy & Utility Planning • General
Ohio Farm Bureau
Buckeye Power and Ohio's Electric Cooperatives developed a data-center load and cost-allocation process in Ohio to prevent existing members from bearing new grid and power costs.
5/25/2026 • Policy & Utility Planning • General
Altoona Mirror
Pennsylvania Governor Josh Shapiro directed the Public Utility Commission in Pennsylvania to develop data-center curtailment, forecasting, reporting, and cost-allocation rules as PJM faces projected capacity shortages.
8/28/2026 • Policy & Utility Planning • General
Additional3 articles · CI Score below 45
LexisNexis State Net / Korey Clark
PJM projected $6.3 billion higher power costs for 13 eastern states and D.C. over three years, citing data centers as the primary peak-demand driver amid New Yorks hyperscale moratorium.
7/22/2026 • Policy & Utility Planning • General
Maryland Daily Record
Maryland primary candidates in 2026 surveyed by the University of Maryland-backed Local News Network largely backed tighter regulations on data center development amid rising residential electricity bills.
6/10/2026 • Policy & Utility Planning • General
WRAL
PJM asked the U.S. Department of Energy for an emergency reliability order that, during extreme heat, allows PJM to require data centers to switch to backup generators.
7/3/2026 • Policy & Utility Planning • General